Permit GraphShortlistSan Francisco building permits since 2000

Ilh Construction Company

Contractor license
335601
State license record
Based in
San Francisco
On San Francisco permits
Oct 2011 to Jun 2026
Last 24 months
1 permit filed

7 permits since 2000: 3 completed, 3 in progress, 1 never finaled.

Of the 1 never-finaled permit, 1 is 5 to 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

AllBathroom remodel 1
FiledOutcomeAddressWork described on the permitDeclared cost
Jun 23, 2026In progress
filed Jun 2026, not yet issued
988 Jackson Strevision to 201707212563.add 3 property line windows on the east side.windows to be of a fire rated assenbly w-60
Details
Permit
202606233775
Status
triage
Filed
Jun 23, 2026
Declared cost
$6,000
Address
988 Jackson St

revision to 201707212563.add 3 property line windows on the east side.windows to be of a fire rated assenbly w-60

Open the permit page

$6,000
May 10, 2024In progress
issued May 2024
2881 Harrison Stpaint roof,recaulk and paint windows, paint exterior where required, waterproofing/caulking at lightwell
Details
Permit
202405101924
Status
issued
Filed
May 10, 2024
Permit issued
May 10, 2024
Declared cost
$35,000
Address
2881 Harrison St

paint roof,recaulk and paint windows, paint exterior where required, waterproofing/caulking at lightwell

Open the permit page

$35,000
May 10, 2024In progress
issued May 2024
2895 Harrison Stpaint roof, recaulk and paint windows, paint exterior where needed.
Details
Permit
202405101927
Status
issued
Filed
May 10, 2024
Permit issued
May 10, 2024
Declared cost
$30,000
Address
2895 Harrison St

paint roof, recaulk and paint windows, paint exterior where needed.

Open the permit page

$30,000
Apr 22, 2019Completed
final sign-off Sep 2019
984 Jackson Stadministrative permit to correct construction type to type-2a. no work under this permit.
Details
Permit
201904228640
Status
complete
Filed
Apr 22, 2019
Permit issued
Jul 24, 2019
Final sign-off
Sep 12, 2019
Address
984 Jackson St

administrative permit to correct construction type to type-2a. no work under this permit.

Open the permit page

Jul 21, 2017Never finaled
issued Mar 2020, no final
988 Jackson Stvertical additon to add 5/f; to expand the top floor apartment with penthouse consisting of three bedrooms and two bathrooms. a total of (n) 1,100 sq ft.
Details
Permit
201707212563
Status
reinstated
Filed
Jul 21, 2017
Permit issued
Mar 4, 2020
Declared cost
$98,000
Address
988 Jackson St

vertical additon to add 5/f; to expand the top floor apartment with penthouse consisting of three bedrooms and two bathrooms. a total of (n) 1,100 sq ft.

Open the permit page

$98,000
Nov 14, 2011Completed
final sign-off Nov 2011
594 19th Avto obtain final inspection for work approved under pa#9620859. all work is complete.
Details
Permit
201111148736
Status
complete
Filed
Nov 14, 2011
Permit issued
Nov 14, 2011
Final sign-off
Nov 16, 2011
Address
594 19th Av

to obtain final inspection for work approved under pa#9620859. all work is complete.

Open the permit page

Oct 26, 2011Completed
final sign-off Nov 2011
594 19th Avrepair and replace existing heat ducts in the garage. add toilet and vanity on the gr floor
Details
Permit
201110267629
Status
complete
Filed
Oct 26, 2011
Permit issued
Nov 9, 2011
Final sign-off
Nov 10, 2011
Declared cost
$1,500
Address
594 19th Av

repair and replace existing heat ducts in the garage. add toilet and vanity on the gr floor