Eco Smart Builder
- Based in
- San Francisco
- On San Francisco permits
- Sep 2019 to Apr 2026
- Last 24 months
- 3 permits filed
55 permits since 2000: 44 completed, 1 in progress, 10 never finaled.
Of the 10 never-finaled permits, 2 are 3 to 5 years old, 8 are 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Deck permits
2 deck permits: 1 completed, 1 never finaled. Typically 0 days from filing to permit and 362 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 13, 2022 | Completed final sign-off Jan 2023 | 2516 Pacific Av | replacement of the membrane at back deck system with a 3-ply layer over system with new flashings and re-installation of back deck as is using trex decking system. all work invisbile from street.Details
replacement of the membrane at back deck system with a 3-ply layer over system with new flashings and re-installation of back deck as is using trex decking system. all work invisbile from street. | $250,000 |
| Oct 14, 2020 | Never finaled issued Oct 2020, no final | 551 25th Av | dry rot repair of to back deck, repair of dry rot at center back deck & stair case, repair dry rot at lower ack deck & installation of plastic decking system on all decks, remove poisioned earthDetails
dry rot repair of to back deck, repair of dry rot at center back deck & stair case, repair dry rot at lower ack deck & installation of plastic decking system on all decks, remove poisioned earth | $21,350 |