Permit GraphShortlistSan Francisco building permits since 2000

C&N Construction Group Inc

Contractor license
1091145
State license record
Based in
Kensington
On San Francisco permits
Jul 2022 to Jan 2025
Last 24 months
1 permit filed

3 permits since 2000: 2 completed, 1 never finaled.

Of the 1 never-finaled permit, 1 is 3 to 5 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

AllStairs 1
FiledOutcomeAddressWork described on the permitDeclared cost
Jan 14, 2025Completed
final sign-off Jun 2025
470 Castro St1st floor: t.i. includes the demo of non-str partitions and building new non-str partitions. all new or revised meps, life safety work will be design - build and submitted separately (bldg is fully sprinkled).
Details
Permit
202501148248
Status
complete
Filed
Jan 14, 2025
Permit issued
Feb 5, 2025
Final sign-off
Jun 27, 2025
Declared cost
$120,000
Address
470 Castro St

1st floor: t.i. includes the demo of non-str partitions and building new non-str partitions. all new or revised meps, life safety work will be design - build and submitted separately (bldg is fully sprinkled).

Open the permit page

$120,000
Jul 20, 2023Completed
final sign-off Dec 2023
2495 San Bruno Avaccessible business entrance abe corrections. requesting technical infesability for ramp rebuild. corrections shown for all other items. abe 201810042260
Details
Permit
202307202631
Status
complete
Filed
Jul 20, 2023
Permit issued
Aug 30, 2023
Final sign-off
Dec 20, 2023
Declared cost
$100
Address
2495 San Bruno Av

accessible business entrance abe corrections. requesting technical infesability for ramp rebuild. corrections shown for all other items. abe 201810042260

Open the permit page

$100
Jul 25, 2022Never finaled
issued Aug 2022, no final
579 19th Avrevision to bpa# 201904228558. show footing and detail for permitted stairs. rear stairs requires footing not shown in originally permitted plans.
Details
Permit
202207259252
Status
issued
Filed
Jul 25, 2022
Permit issued
Aug 1, 2022
Declared cost
$1,000
Address
579 19th Av

revision to bpa# 201904228558. show footing and detail for permitted stairs. rear stairs requires footing not shown in originally permitted plans.

Open the permit page

$1,000
C&N Construction Group Inc, contractor license 1091145 | Permit Graph