Berisha Construction
- Based in
- San Jose
- On San Francisco permits
- Nov 2015 to Feb 2019
- Last 24 months
- 0 permits filed
2 permits since 2000: 2 completed.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Deck permits
1 deck permit: 1 completed. Typically 18 days from filing to permit and 1841 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Nov 16, 2015 | Completed final sign-off Dec 2020 | 1251 37th Av | revision to app#201508144323. lower slab and convert extg non-habitable space to new habitable space. replace extg interior stair. revise new deck.Details
revision to app#201508144323. lower slab and convert extg non-habitable space to new habitable space. replace extg interior stair. revise new deck. | $109,000 |