7 permits since 2000: 6 completed, 1 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 21, 2026 | In progress issued Jul 2026 | 200 Dolores St | replacement of 2 deteriorated beams in kind, remove/repl the subfloor balcony on (2nd and 3rd floors).put new torch down roof. separate hot works permit req'd from sffdDetails
replacement of 2 deteriorated beams in kind, remove/repl the subfloor balcony on (2nd and 3rd floors).put new torch down roof. separate hot works permit req'd from sffd | $30,000 |
| Nov 21, 2025 | Completed final sign-off Feb 2026 | 245 Delano Av | remodel bathroom demolish (e) drywall and ceiling. new electrical 4 lights and outlet. plumbing, install new shower valve the existing one is a shower pan, will convert into a bath tubDetails
remodel bathroom demolish (e) drywall and ceiling. new electrical 4 lights and outlet. plumbing, install new shower valve the existing one is a shower pan, will convert into a bath tub | $16,000 |
| Oct 10, 2025 | Completed final sign-off Dec 2025 | 3177 California St | bathroom remodeling install new bath tub, install shower valve and add one new light in the ceiling, we are not going to demolish the entire bathroom, we only demolishing around the bath tub for installing the new bath tub, same size, same location, same materialDetails
bathroom remodeling install new bath tub, install shower valve and add one new light in the ceiling, we are not going to demolish the entire bathroom, we only demolishing around the bath tub for installing the new bath tub, same size, same location, same material | $8,000 |
| Sep 15, 2025 | Completed final sign-off Oct 2025 | 243 Granada Av | add new non load bearing wall on the 1st fl and replace electrical switch.Details
add new non load bearing wall on the 1st fl and replace electrical switch. | $3,000 |
| Apr 17, 2025 | Completed final sign-off May 2025 | 200 Dolores St | replace 4 sheets tile 12 x 24 outside of the building. no structural damage.Details
replace 4 sheets tile 12 x 24 outside of the building. no structural damage. | $1,200 |
| Jul 23, 2024 | Completed final sign-off Jan 2025 | 200 Dolores St | interior bathroom remodel. remove and replace portions of non bearing wallsDetails
interior bathroom remodel. remove and replace portions of non bearing walls | $10,000 |
| May 23, 2024 | Completed final sign-off Jan 2025 | 660 Alvarado St | first bathroom remodel to include remove (e) bathtub and install new tub and shower surround wall with new tile for the wall and floor. install shower valve. second bathroom remodel to replace shower pan and valve with new tiling for wall and floor. no wall removal or structural workDetails
first bathroom remodel to include remove (e) bathtub and install new tub and shower surround wall with new tile for the wall and floor. install shower valve. second bathroom remodel to replace shower pan and valve with new tiling for wall and floor. no wall removal or structural work | $12,000 |