Block 6778, lot 010
50 San Gabriel Ave
- City’s use
- Single Family Residential
- Built
- 1924
- Stories
- 1
- Units
- 1
- Rooms
- 1 bathroom
- Building
- 1,275 sq ft
- Lot
- 3,131 sq ft
- Zoning
- RH1
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
9 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 25, 2022 | Completed final sign-off Feb 2023 | 50 San Gabriel Av | removation of kitchen/office & bathroom on main floor. (1) doorway to be shifted between kitchen/office, expand kitchen, reducing office space.Details
removation of kitchen/office & bathroom on main floor. (1) doorway to be shifted between kitchen/office, expand kitchen, reducing office space. | $100,000 | |
| Dec 16, 2015 | Never finaled issued Dec 2015, no final | 50 San Gabriel Av | street spaceDetails
street space | ||
| Apr 29, 2015 | Completed final sign-off May 2015 | 50 San Gabriel Av | Tom Lee Roofing Inc. | re-roofingDetails
re-roofing | $14,900 |
| Dec 18, 2013 | Never finaled issued Dec 2013, no final | 50 San Gabriel Av | street spaceDetails
street space | ||
| Dec 9, 2002 | Completed final sign-off Aug 2003 | 50 San Gabriel Av | Andrew Mihailovsky | move furnace & water heater, install washer/dryer/utility sinkDetails
move furnace & water heater, install washer/dryer/utility sink | $1,000 |
| Dec 6, 2002 | Completed final sign-off Jan 2003 | 50 San Gabriel Av | build an outdoor stationary charcoal grill (barbeque) in backyard.Details
build an outdoor stationary charcoal grill (barbeque) in backyard. | $400 | |
| Nov 25, 2002 | Never finaled issued Nov 2002, no final | 50 San Gabriel Av | Andrew Mihailovsky | replace foundations under 3 center posts w/ a 3ftx3ft,12"below grade spread footing w/ #4 rebar ea.wDetails
replace foundations under 3 center posts w/ a 3ftx3ft,12"below grade spread footing w/ #4 rebar ea.w | $1,000 |
| Nov 8, 2002 | Completed final sign-off Aug 2003 | 50 San Gabriel Av | Andrew Mihailovsky | reinstall legal bathroom on 1st floor. finish storage space on 1st floorDetails
reinstall legal bathroom on 1st floor. finish storage space on 1st floor | $10,000 |
| Jun 14, 2002 | Completed final sign-off Nov 2002 | 50 San Gabriel Av | Andrew Mihailovsky | remove kitchen/stud wall/elec. work/closet, open walls & ceiling as needed to correct nov#200227742Details
remove kitchen/stud wall/elec. work/closet, open walls & ceiling as needed to correct nov#200227742 | $3,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Andrew Mihailovsky (4), Tom Lee Roofing Inc.
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover single-family homes like this one.