Block 6655, lot 024A
150 Randall St
- City’s use
- Single Family Residential
- Built
- 1924
- Stories
- 1
- Units
- 1
- Rooms
- 3 bedrooms, 3 bathrooms
- Building
- 2,757 sq ft
- Lot
- 2,247 sq ft
- Zoning
- RH2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
33 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 22, 2024 | Completed final sign-off Jan 2025 | 150 Randall St | Level 8 Construction Inc | to obtain final inspection for work approved under #201704033878, 201712186762, 201807033618. all work is complete.Details
to obtain final inspection for work approved under #201704033878, 201712186762, 201807033618. all work is complete. | |
| Mar 22, 2024 | Completed final sign-off Apr 2024 | 150 Randall St | Level 8 Construction Inc | change material type for railings - pa# 201704033878. cable rail to glass panel at roof deck @ front of bldgDetails
change material type for railings - pa# 201704033878. cable rail to glass panel at roof deck @ front of bldg | |
| Mar 22, 2024 | In progress issued Mar 2024 | 150 Randall St | Level 8 Construction Inc | to obtain final inspection for work approved under pa# 2011-06-24-8922. all work is complete.Details
to obtain final inspection for work approved under pa# 2011-06-24-8922. all work is complete. | |
| Sep 20, 2023 | Never finaled filed Sep 2023, never issued | 150 Randall St | revision changes to pa#202201146004. power walls & equipment relocated per customer requestDetails
revision changes to pa#202201146004. power walls & equipment relocated per customer request | $500 | |
| Dec 30, 2022 | Expired or cancelled expired Mar 2024 | 150 Randall St | to obtain final inspection for work approved under pa# 201807033618. all work is complete.Details
to obtain final inspection for work approved under pa# 201807033618. all work is complete. | ||
| Aug 25, 2022 | Expired or cancelled cancelled Jan 2026 | 150 Randall St | Sculpt Gardens Inc | increase height of (e) fence from 6ft to 8ft on 3 sides including side sidewalk side with gate. above 6ft with lattice.Details
increase height of (e) fence from 6ft to 8ft on 3 sides including side sidewalk side with gate. above 6ft with lattice. | $10,000 |
| Jan 14, 2022 | Never finaled issued Mar 2022, no final | 150 Randall St | Tesla Energy Operations | install energy storage system @ 27 kwh (2) batteries plus n200a internal load center.Details
install energy storage system @ 27 kwh (2) batteries plus n200a internal load center. | $14,400 |
| Jul 9, 2020 | Never finaled issued Jul 2020, no final | 150 Randall St | street space | ||
| Jun 3, 2020 | Expired or cancelled expired Mar 2024 | 150 Randall St | renew pa# 201712186762, 201704133878, 201106248922 for final inspection.Details
renew pa# 201712186762, 201704133878, 201106248922 for final inspection. | ||
| Jan 8, 2020 | Never finaled issued Jan 2020, no final | 150 Randall St | street space | ||
| Nov 1, 2019 | Never finaled issued Nov 2019, no final | 150 Randall St | street space | ||
| Sep 16, 2019 | Never finaled issued Sep 2019, no final | 150 Randall St | street space | ||
| Sep 16, 2019 | Never finaled issued Sep 2019, no final | 150 Randall St | street space | ||
| Jun 24, 2019 | Never finaled issued Jun 2019, no final | 150 Randall St | street space | ||
| Jun 13, 2019 | Never finaled issued Jun 2019, no final | 150 Randall St | street space | ||
| May 10, 2019 | Completed final sign-off Jul 2020 | 150 Randall St | San Francisco Fire Protection | fire alarm sprinkler monitoring, heat detector, manual pul, facp, monitoring module will be installed in the garage.Details
fire alarm sprinkler monitoring, heat detector, manual pul, facp, monitoring module will be installed in the garage. | $5,000 |
| Dec 17, 2018 | Never finaled issued Dec 2018, no final | 150 Randall St | street space | ||
| Sep 10, 2018 | Never finaled issued Sep 2018, no final | 150 Randall St | street space | ||
| Jul 3, 2018 | Expired or cancelled expired Jul 2022 | 150 Randall St | Level 8 Construction Inc | rev to pa# 2011/06/24/8922, pa# 2017/04/13/3878 & pa# 2017/12/18/6762. response to stop work nov# 201868281. new framing to address dry rot damage & structural work. remove & replace (e) exterior finishes to address lack of exterior sheathing over studs. demo calcs include as required.Details
rev to pa# 2011/06/24/8922, pa# 2017/04/13/3878 & pa# 2017/12/18/6762. response to stop work nov# 201868281. new framing to address dry rot damage & structural work. remove & replace (e) exterior finishes to address lack of exterior sheathing over studs. demo calcs include as required. | $15,000 |
| Jun 25, 2018 | Never finaled issued Jun 2018, no final | 150 Randall St | street space | ||
| Jun 8, 2018 | Completed final sign-off Jul 2020 | 150 Randall St | New Era Construction Llc, A Plumbing Company | install new fire sprinkler system through out building per nfpa 13r total (58), sprinkler heads and 2" underground service. ref pa #2017-1218-6762. nfpa 13 in garage sprinkler monitoring sep permit. nfpa 24 undergroundDetails
install new fire sprinkler system through out building per nfpa 13r total (58), sprinkler heads and 2" underground service. ref pa #2017-1218-6762. nfpa 13 in garage sprinkler monitoring sep permit. nfpa 24 underground | $20,000 |
| Mar 5, 2018 | Never finaled issued Mar 2018, no final | 150 Randall St | street space | ||
| Dec 18, 2017 | Never finaled issued Mar 2018, no final | 150 Randall St | Level 8 Construction Inc | revision to permit #201106248922 s1 & 201704133878 - changed cable rails to glass rails, add skylights, add fire rated window to garage. revised location of some interior doors. new doors & slab into existing lightwell.Details
revision to permit #201106248922 s1 & 201704133878 - changed cable rails to glass rails, add skylights, add fire rated window to garage. revised location of some interior doors. new doors & slab into existing lightwell. | $14,000 |
| Dec 11, 2017 | Never finaled issued Dec 2017, no final | 150 Randall St | street space | ||
| Sep 28, 2017 | Never finaled issued Sep 2017, no final | 150 Randall St | street space | ||
| Aug 16, 2017 | Never finaled issued Aug 2017, no final | 150 Randall St | street space | ||
| Apr 13, 2017 | Never finaled issued Jul 2017, no final | 150 Randall St | Level 8 Construction Inc | revision to 201106248922 s/1: moving of internal wall and relocation of the kitchen and master bathroom, add powder rm @3rd. move laundry into garage & remove shop space in garage. exterior windows revised. hvac system changed to hydronic system, framing changes. no heated space added.Details
revision to 201106248922 s/1: moving of internal wall and relocation of the kitchen and master bathroom, add powder rm @3rd. move laundry into garage & remove shop space in garage. exterior windows revised. hvac system changed to hydronic system, framing changes. no heated space added. | |
| Feb 1, 2017 | Never finaled issued Feb 2017, no final | 150 Randall St | street space | ||
| Jul 16, 2012 | Never finaled issued Jul 2012, no final | 150 Randall St | street space | ||
| Mar 5, 2012 | Completed final sign-off Mar 2012 | 150 Randall St | Excelsior Roofing Company | reroofingDetails
reroofing | $10,915 |
| Jun 24, 2011 | Never finaled issued Oct 2012, no final | 150 Randall St | remodel to (e) residence. second flr to be reorganized to provide improved kitchen & new family room at the rear of the house. a new 3rd flr addition will contain 2 new bedrooms & 1 bathroom. vertical addition only.Details
remodel to (e) residence. second flr to be reorganized to provide improved kitchen & new family room at the rear of the house. a new 3rd flr addition will contain 2 new bedrooms & 1 bathroom. vertical addition only. | $300,000 | |
| Mar 20, 2007 | Never finaled issued Mar 2007, no final | 150 Randall St | street space permit | ||
| Apr 20, 2005 | Never finaled issued Apr 2005, no final | 150 Randall St | street space & sidewalk repair |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Level 8 Construction Inc (6), A Plumbing Company, Excelsior Roofing Company, New Era Construction Llc, San Francisco Fire Protection, Sculpt Gardens Inc, Tesla Energy Operations
- Architects
- Edward Kaplan (4)
- Engineers
- Shaun E. Moynahan
- Designers
- Fai Wong
Find contractors for work like this