Block 6533, lot 007
1336 Guerrero St
26 permits filed for this property since 2000.
CompletedIn progressNever finaledExpired or cancelled
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 13, 2026 | Completed | 1336 Guerrero St | Badger Builders Dba Badger Engineering B | add bathroom where existing laundry room is. 3rd floor | $10,000 |
| Mar 31, 2026 | In progress | 1330 Guerrero St | Badger Builders Dba Badger Engineering B | unit 1330b: convert existing pantry into a three-quarter bathroom. | $12,000 |
| Aug 4, 2025 | Completed | 1336 Guerrero St | Badger Builders Dba Badger Engineering B | 1336a guerrero st - converting pantry area into full bathroom. | $6,000 |
| Aug 7, 2024 | Expired or cancelled | 1330 Guerrero St | Brent Harris Engineering Construction | bathroom remodel to include replacing bathtub and tiles. rewiring old knob and tube subpanel. | $10,000 |
| Feb 23, 2022 | Never finaled | 1330 Guerrero St | recommencement and completion of work approved under previous permit #200708291215. 40% of work remaining. | ||
| Feb 23, 2022 | Completed | 1334 Guerrero St | to obtain a final inspection for work approved under previous permit 200801041851. all work is complete. | ||
| Feb 7, 2022 | Completed | 1334 Guerrero St | Cht Properties Development | to obtain a final inspection for work approved under prevoius pa 200805303233. all work is complete. | |
| Dec 16, 2021 | Completed | 1332 Guerrero St | patch drywall. removing old trim around where a door used to be. | $500 | |
| Feb 17, 2021 | Completed | 1336 Guerrero St | remove non-structural wall between living room and kitchen | $1,750 | |
| Mar 12, 2020 | Never finaled | 1334 Guerrero St | street space | ||
| Nov 21, 2019 | Never finaled | 1330 Guerrero St | street space | ||
| Nov 4, 2019 | Completed | 1334 Guerrero St | repair and replace 50 sqft of cracking lath and plaster with sheetrock. within unit inside room. | $400 | |
| Oct 24, 2019 | Completed | 1336 Guerrero St | repair dryrot in south west corner of the building on siding approx area 2 sf. no structural work. | $300 | |
| Jun 4, 2019 | Completed | 1336 Guerrero St | bathroom tiles around bathtub replacement. replace sink. approximately 6' x 9' | $450 | |
| May 3, 2019 | Completed | 1336 Guerrero St | removing non-structural wall between living room & kitchen. | $1,750 | |
| May 2, 2019 | Completed | 1332 Guerrero St | Pacific Polymers Dba American Foam Exp | reroofing | $24,994 |
| Mar 28, 2019 | Never finaled | 1330 Guerrero St | street space | ||
| Mar 20, 2019 | Completed | 1330 Guerrero St | S F Garage Company Inc. | revision to soft story permit 201708165051 | $10,000 |
| Aug 16, 2017 | Completed | 1330 Guerrero St | soft story : upgrade per sfebc chapter 4d, design criteria from 2016 iebc appendix a-4. | $20,000 | |
| Jun 6, 2008 | Never finaled | 1334 Guerrero St | street space & sidewalk permit only. | ||
| May 30, 2008 | Expired or cancelled | 1334 Guerrero St | Cht Properties Development | remodel kitchen and bathroom, flouresent lights in kitchen and bathroom. no structural work. | $7,000 |
| Mar 6, 2008 | Never finaled | 1330 Guerrero St | street space permit only. | ||
| Jan 4, 2008 | Expired or cancelled | 1330 Guerrero St | revision to pa# 2007/09/26/3766 to change configuration of proposed bathroom in unit 1334 on the 1st floor. | ||
| Dec 14, 2007 | Never finaled | 1330 Guerrero St | to comply with notice of violation complaint#200728530. repair side stairs, electreical , plumbing per complaint. | $3,000 | |
| Sep 26, 2007 | Expired or cancelled | 1330 Guerrero St | removal of non-bearing walls and infill. remodel and enlarge bathroom at kitchen area. no structural work. all work under this permit to be done in unit 1334. | $6,000 | |
| Aug 29, 2007 | Never finaled | 1330 Guerrero St | change coutnertop, install new cabinets, refinish or install new flooring, install tile, change sink, change toilets, change shower heads, new vinyl floors. no structural work. total 6 kitchens & 6 bathrooms. | $80,000 |