Permit GraphShortlistSan Francisco building permits since 2000

Block 6309D, lot 004

232 Talbert St

City’s use
Multi-Family Residential
Built
1941
Stories
1
Units
2
Rooms
2 bathrooms
Building
1,260 sq ft
Lot
2,500 sq ft
Zoning
RH1
Construction type
NA

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

4 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Apr 21, 2026Completed
final sign-off May 2026
232 Talbert StCkg Construction & Roofing Corpre-roofing: remove and replace roofing material / existing roofing material (in-kind)
Details
Permit
202604219774
Status
complete
Filed
Apr 21, 2026
Permit issued
Apr 21, 2026
Final sign-off
May 12, 2026
Declared cost
$13,000
Address
232 Talbert St

re-roofing: remove and replace roofing material / existing roofing material (in-kind)

Open the permit page

$13,000
Jun 19, 2019Never finaled
filed Jun 2019, never issued
232 Talbert StA J Constructionremove connecting stairs from upper unit to garage to comply with nov 201803671. install 1 hr wall on lower level, remove 1 window (bathroom)
Details
Permit
201906193910
Status
filed
Filed
Jun 19, 2019
Declared cost
$4,000
Address
232 Talbert St

remove connecting stairs from upper unit to garage to comply with nov 201803671. install 1 hr wall on lower level, remove 1 window (bathroom)

Open the permit page

$4,000
Mar 8, 2019Completed
final sign-off Oct 2020
232 Talbert StA J Constructionrepair stairs inside from upper unit to garage to correct nov 201803671
Details
Permit
201903084817
Status
complete
Filed
Mar 8, 2019
Permit issued
Mar 8, 2019
Final sign-off
Oct 15, 2020
Declared cost
$2,000
Address
232 Talbert St

repair stairs inside from upper unit to garage to correct nov 201803671

Open the permit page

$2,000
Oct 18, 2018Never finaled
issued Oct 2018, no final
232 Talbert StA J Constructionremove existing 2 temporary main panles and replace with 2 main meters. reframe mounting structure for panels, re-pipe water supply for upper toilet. re-patch wall inside bathroom as effected by re-piping to comply with nov 201891401 #2
Details
Permit
201810183577
Status
issued
Filed
Oct 18, 2018
Permit issued
Oct 18, 2018
Declared cost
$3,500
Address
232 Talbert St

remove existing 2 temporary main panles and replace with 2 main meters. reframe mounting structure for panels, re-pipe water supply for upper toilet. re-patch wall inside bathroom as effected by re-piping to comply with nov 201891401 #2

Open the permit page

$3,500

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
A J Construction (3), Ckg Construction & Roofing Corp

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover two-family buildings like this one.