18 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 9, 2013 | Never finaled issued Aug 2013, no final | 999 Felton St | street space permitDetails
street space permit | ||
| Jun 28, 2013 | Never finaled issued Jun 2013, no final | 999 Felton St | streeet spaceDetails
streeet space | ||
| Jan 18, 2013 | Never finaled issued Jan 2013, no final | 999 Felton St | street spaceDetails
street space | ||
| Jan 14, 2011 | Completed final sign-off Jun 2011 | 801 Felton St | Monterey Mechanical Co | 80 kw generator installation plan check revision to permit application #20105142477,201006104237,201006245255. detail changes. added secondary containment fill w/95%, audible alarm, leak sensor.Details
80 kw generator installation plan check revision to permit application #20105142477,201006104237,201006245255. detail changes. added secondary containment fill w/95%, audible alarm, leak sensor. | |
| Jun 24, 2010 | Never finaled issued Jun 2010, no final | 801 Felton St | Monterey Mechanical Co | revision to 201005142477 and 201006104237. detail changes for 80 kw generator installationDetails
revision to 201005142477 and 201006104237. detail changes for 80 kw generator installation | |
| Jun 10, 2010 | Never finaled issued Jun 2010, no final | 801 Felton St | Monterey Mechanical Co | revision to pa# 2010.05.14.2477. tank, venting and generator type changedDetails
revision to pa# 2010.05.14.2477. tank, venting and generator type changed | |
| May 14, 2010 | Never finaled issued May 2010, no final | 801 Felton St | Monterey Mechanical Co | installation of 80 kw genset with leak detectionDetails
installation of 80 kw genset with leak detection | $150,000 |
| Apr 30, 2010 | Never finaled issued Apr 2010, no final | 999 Felton St | street space permitDetails
street space permit | ||
| Jan 4, 2010 | Never finaled issued Jan 2010, no final | 999 Felton St | street spaceDetails
street space | ||
| Sep 30, 2009 | Never finaled issued Sep 2009, no final | 999 Felton St | street spaceDetails
street space | ||
| Sep 21, 2009 | Never finaled issued Sep 2009, no final | 999 Felton St | street spaceDetails
street space | ||
| Apr 10, 2009 | Never finaled issued Apr 2009, no final | 800 Bacon St | street space & sidewalk permit only.Details
street space & sidewalk permit only. | ||
| Mar 10, 2009 | Never finaled issued May 2009, no final | 801 Felton St | Monterey Mechanical Co | installation of 10,000 gal underground diesel fuel storage tank. install 2 day tanks 150 gal each. install double containment flex hose supply, return, & vent lines underground. install double contained steel lines above gorund. installation of 4 rupture basins.Details
installation of 10,000 gal underground diesel fuel storage tank. install 2 day tanks 150 gal each. install double containment flex hose supply, return, & vent lines underground. install double contained steel lines above gorund. installation of 4 rupture basins. | $250,000 |
| Feb 27, 2009 | Never finaled issued Mar 2009, no final | 800 Bacon St | Intrepid Electronic Systems Inc | fire alarm system of new vehicle/material storage building, consisting of (1) fire alarm control panel, (5) manual pull stations (1) smoke detector above control panel, (16) heat detectors, (8) horn/strobe combination.Details
fire alarm system of new vehicle/material storage building, consisting of (1) fire alarm control panel, (5) manual pull stations (1) smoke detector above control panel, (16) heat detectors, (8) horn/strobe combination. | $12,000 |
| Oct 30, 2008 | Never finaled issued Oct 2008, no final | 800 Bacon St | street space & sidewalk repair.Details
street space & sidewalk repair. | ||
| Aug 26, 2008 | Never finaled issued Jan 2009, no final | 801 Felton St | Sabah International Incorporated | install final & test fire supp system, 5 control panels, 11 photo det, 8 pull station, 7 imput module, 1 horn/strobe, 10 ion det., 6 abort, 16 strobes, 2 dual sync mod., 10 nozzles.Details
install final & test fire supp system, 5 control panels, 11 photo det, 8 pull station, 7 imput module, 1 horn/strobe, 10 ion det., 6 abort, 16 strobes, 2 dual sync mod., 10 nozzles. | $117,675 |
| Aug 14, 2008 | Never finaled issued Nov 2008, no final | 801 Felton St | Walschon Fire Protection Inc | install wet pipe fire sprinkler system begining 6 inches above finished floor-101 headsDetails
install wet pipe fire sprinkler system begining 6 inches above finished floor-101 heads | $97,497 |
| Apr 29, 2002 | Expired or cancelled expired May 2006 | 801 Felton St | Lc General Engineering & Construction | replace mechanical equipment & associated electrical work, minor structural & architectural improvemDetails
replace mechanical equipment & associated electrical work, minor structural & architectural improvem | $100,000 |