Block 5731, lot 002
291 Putnam St
- City’s use
- Multi-Family Residential
- Built
- 1996
- Units
- 46
- Rooms
- 112 bedrooms, 48 bathrooms
- Building
- 38,000 sq ft
- Lot
- 38,507 sq ft
- Zoning
- NCS
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
12 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 12, 2024 | In progress issued Apr 2024 | 291 Putnam St | Premier Security Solutions Corp | db testing to verify sound level in sleeping areas, complying with sffc sectin 1103.7.6.1Details
db testing to verify sound level in sleeping areas, complying with sffc sectin 1103.7.6.1 | |
| Mar 29, 2024 | In progress issued Apr 2024 | 211 Putnam St | Premier Security Solutions Corp | to verify (e) sound level in sleeping areas comply w/ffc sec 1103.7.6.1Details
to verify (e) sound level in sleeping areas comply w/ffc sec 1103.7.6.1 | |
| Aug 10, 2022 | Completed final sign-off Sep 2022 | 211 Putnam St | Blu Sky Restoration Contractors Llc | to comply with 202291733: exterior stairway less than 50%. damage framing and siding.Details
to comply with 202291733: exterior stairway less than 50%. damage framing and siding. | $15,000 |
| Nov 8, 2019 | Completed final sign-off Nov 2019 | 1000 Tompkins Av | Walschon Fire Protection Inc | revision to app#201905291868. added 4 sprinkler under the suspendid ceiling. added 1 sprinkler in riser room. added 1 sprinkler in closet. add 6 sprinkler underneath the sub floor.Details
revision to app#201905291868. added 4 sprinkler under the suspendid ceiling. added 1 sprinkler in riser room. added 1 sprinkler in closet. add 6 sprinkler underneath the sub floor. | $14,827 |
| Sep 19, 2019 | Never finaled issued Sep 2019, no final | 1000 Tompkins Av | street spaceDetails
street space | ||
| Sep 4, 2019 | Never finaled issued Sep 2019, no final | 1000 Tompkins Av | street spaceDetails
street space | ||
| Jun 5, 2019 | Never finaled issued Jun 2019, no final | 1000 Tompkins Av | street spaceDetails
street space | ||
| May 29, 2019 | Completed final sign-off Dec 2019 | 1000 Tompkins Av | Midstate Construction Corporation | revision to 2018-1210-7904 (original pa) & 2019-0213-2834 (revision to pa 2018-1210-7904) - structural construction system for the new community room, kitchen and accessible restroomsDetails
revision to 2018-1210-7904 (original pa) & 2019-0213-2834 (revision to pa 2018-1210-7904) - structural construction system for the new community room, kitchen and accessible restrooms | |
| May 29, 2019 | Completed final sign-off Feb 2020 | 1000 Tompkins Av | Walschon Fire Protection Inc | relocate 6 sprinkler pendents to accomodate new partition plan. relocate 4" horiz piping along with 2" drain due to layout. no seismic upgrades in area of workDetails
relocate 6 sprinkler pendents to accomodate new partition plan. relocate 4" horiz piping along with 2" drain due to layout. no seismic upgrades in area of work | $14,827 |
| Feb 13, 2019 | Completed final sign-off Dec 2019 | 1000 Tompkins Av | Midstate Construction Corporation | ref pa#201812107904; rev to the structural constructon system for the construction of the new community room, kitchen, and accessible restrooms.Details
ref pa#201812107904; rev to the structural constructon system for the construction of the new community room, kitchen, and accessible restrooms. | |
| Dec 10, 2018 | Completed final sign-off Dec 2019 | 1000 Tompkins Av | Midstate Construction Corporation | selected replacement of unit interior items & finishes per unit interior replacement schedule; paint ext surfaces; replacement of e w/h: see units; renovate of e leasing office & laundry; new community rm, kitchen, & accessible restrms; new landscape & play structure & ground finishes @ e courtyard;Details
selected replacement of unit interior items & finishes per unit interior replacement schedule; paint ext surfaces; replacement of e w/h: see units; renovate of e leasing office & laundry; new community rm, kitchen, & accessible restrms; new landscape & play structure & ground finishes @ e courtyard; | $2,900,000 |
| Mar 27, 2008 | Completed final sign-off Feb 2009 | 211 Putnam St | replace manufacturer defective particle board, exterior siding with new cement board siding in kind. no structural work, no change to (e) rated assembliesDetails
replace manufacturer defective particle board, exterior siding with new cement board siding in kind. no structural work, no change to (e) rated assemblies | $75,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Midstate Construction Corporation (3), Premier Security Solutions Corp (2), Walschon Fire Protection Inc (2), Blu Sky Restoration Contractors Llc
- Architects
- Daniel Levine (2)
- Engineers
- Matthew Tropp, Matthew Tropp, Rene Santos, Steve H. Kang