Permit GraphShortlistSan Francisco building permits since 2000

Block 5215, lot 021

1680 Davidson Ave

City’s use
Industrial
Built
1966
Stories
1
Lot
57,163 sq ft
Zoning
M2
Construction type
D

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

4 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Sep 28, 2026Completed
final sign-off Oct 2026
1680 Davidson AvCoil Increvision to permit # 202604230014: reduced scope 31 chargers installed. 17 ev make ready w/ foundation, junction boxes, wiring and bollards.
Details
Permit
202609288714
Status
complete
Filed
Sep 28, 2026
Permit issued
Sep 29, 2026
Final sign-off
Oct 2, 2026
Address
1680 Davidson Av

revision to permit # 202604230014: reduced scope 31 chargers installed. 17 ev make ready w/ foundation, junction boxes, wiring and bollards.

Open the permit page

Apr 23, 2026Completed
final sign-off Oct 2026
1680 Davidson AvCoil Incinstall 480v, 4000amp service. install 4 - 1000 amp panels. 48 bew 40kw and 60 kw ev fast dc charger.
Details
Permit
202604230014
Status
complete
Filed
Apr 23, 2026
Permit issued
Apr 24, 2026
Final sign-off
Oct 2, 2026
Declared cost
$190,000
Address
1680 Davidson Av

install 480v, 4000amp service. install 4 - 1000 amp panels. 48 bew 40kw and 60 kw ev fast dc charger.

Open the permit page

$190,000
May 25, 2023Completed
final sign-off Mar 2025
1680 Davidson AvR G C Construction Increvision to 202109218869: update painted ada pathway stripping to relocated main entrance. no other alteration or changes.
Details
Permit
202305258628
Status
complete
Filed
May 25, 2023
Permit issued
May 26, 2023
Final sign-off
Mar 13, 2025
Address
1680 Davidson Av

revision to 202109218869: update painted ada pathway stripping to relocated main entrance. no other alteration or changes.

Open the permit page

Sep 21, 2021Completed
final sign-off Mar 2025
1680 Davidson AvPpc Construction Management, R G C Construction Increspond to nov 202180316. change of use to private parking lot. legalize removal of 2 (e) canopy structures onsite. legalize repaving of entire ste. add new ada restrooms in (e) storage area. replace hvac units. install 2 (n) ext doors & 1 interior pass thru window
Details
Permit
202109218869
Status
complete
Filed
Sep 21, 2021
Permit issued
Dec 8, 2021
Final sign-off
Mar 7, 2025
Declared cost
$137,000
Address
1680 Davidson Av

respond to nov 202180316. change of use to private parking lot. legalize removal of 2 (e) canopy structures onsite. legalize repaving of entire ste. add new ada restrooms in (e) storage area. replace hvac units. install 2 (n) ext doors & 1 interior pass thru window

Open the permit page

$137,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Coil Inc (2), R G C Construction Inc (2), Ppc Construction Management
Engineers
Damir Rahman (2), Thomas Moll

Find contractors for work like this