Block 3622, lot 002
806 Noe St
- City’s use
- Single Family Residential
- Built
- 1908
- Stories
- 2
- Units
- 1
- Rooms
- 4 bedrooms, 3 bathrooms
- Building
- 2,209 sq ft
- Lot
- 2,000 sq ft
- Zoning
- RH2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
11 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 23, 2025 | Completed final sign-off Aug 2026 | 806 Noe St | 415 Design+Build | horizontal infill addition - convert recessed porch into habitable space (n) exterior spiral stair to grade. 1st flr- as required to bring down structural loads. 2nd flr - convert porch to habitable; remove wall btwn kitchen and dining. 3rd flr no work.Details
horizontal infill addition - convert recessed porch into habitable space (n) exterior spiral stair to grade. 1st flr- as required to bring down structural loads. 2nd flr - convert porch to habitable; remove wall btwn kitchen and dining. 3rd flr no work. | $101,013 |
| Apr 13, 2023 | Completed final sign-off Oct 2023 | 806 Noe St | 415 Design+Build | remodel 2 bathrooms on the top fl. both in like kindDetails
remodel 2 bathrooms on the top fl. both in like kind | $50,000 |
| Mar 31, 2023 | Completed final sign-off Apr 2023 | 806 Noe St | 415 Design+Build | to comply with nov# 201812521: installed garage door w/ out permit.Details
to comply with nov# 201812521: installed garage door w/ out permit. | $1,000 |
| Mar 31, 2023 | Completed final sign-off Oct 2023 | 806 Noe St | 415 Design+Build | remodel - all in like kind - bathroom ground floorDetails
remodel - all in like kind - bathroom ground floor | $32,000 |
| May 29, 2018 | Completed final sign-off Dec 2018 | 806 Noe St | S Mc Cann Construction Inc | facade and exterior stairs remodelDetails
facade and exterior stairs remodel | $7,500 |
| Nov 4, 2015 | Completed final sign-off Jun 2016 | 806 Noe St | Clayton Valley Construction Inc | remove existing cabinets in ground floor office nook, install new cabinets and counter tops. replace in-kind, no structural work.Details
remove existing cabinets in ground floor office nook, install new cabinets and counter tops. replace in-kind, no structural work. | $5,000 |
| Sep 8, 2014 | Completed final sign-off Dec 2014 | 806 Noe St | Clayton Valley Construction Inc | remove existing tile wall & hearth at fireplace, remove trim & lath & plaster, prep for installation of new gas fireplace with direct vent located on 2nd floor at (e) location. re-sheetrock & install new tile hearth and surround. no structural alternation to existing framing. located at 2nd floorDetails
remove existing tile wall & hearth at fireplace, remove trim & lath & plaster, prep for installation of new gas fireplace with direct vent located on 2nd floor at (e) location. re-sheetrock & install new tile hearth and surround. no structural alternation to existing framing. located at 2nd floor | $4,000 |
| Jul 25, 2014 | Completed final sign-off Aug 2014 | 806 Noe St | Sarris Construction | replace 5 windows with marvin wood clad insulated glass in kind. all visible from street.Details
replace 5 windows with marvin wood clad insulated glass in kind. all visible from street. | $6,000 |
| Mar 8, 2013 | Completed final sign-off Jun 2013 | 806 Noe St | revision to pa# 2012-0523-1113-request by city inspectors for approved plans & holddown scheduleDetails
revision to pa# 2012-0523-1113-request by city inspectors for approved plans & holddown schedule | ||
| Nov 6, 2012 | Completed final sign-off Jun 2013 | 806 Noe St | new foundation at ground floor; revision to permit 201205231113, lower slab and foundation in laundry areaDetails
new foundation at ground floor; revision to permit 201205231113, lower slab and foundation in laundry area | $10,000 | |
| May 23, 2012 | Completed final sign-off Jun 2013 | 806 Noe St | kitchen, bath remodel, add one bathroom, convert extg storage to family and laundry room, replace some windows not visible from the street, add balcony on extg roof, tile, paint.dig out partial basement, some structural bracing and improvements.Details
kitchen, bath remodel, add one bathroom, convert extg storage to family and laundry room, replace some windows not visible from the street, add balcony on extg roof, tile, paint.dig out partial basement, some structural bracing and improvements. | $25,000 |