Block 3570, lot 048

2075 Mission St

City’s use
Commercial Retail
Built
1918
Stories
3
Rooms
2 bathrooms
Building
15,750 sq ft
Lot
5,248 sq ft
Zoning
NC3
Construction type
D

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

18 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Mar 14, 2022Completed
final sign-off Sep 2022
2075 Mission StGolden Gate Sign Company Inc.intalling (1) projecting sign "union station"
Details
Permit
202203149890
Status
complete
Filed
Mar 14, 2022
Permit issued
Mar 14, 2022
Final sign-off
Sep 15, 2022
Declared cost
$10,000
Address
2075 Mission St

intalling (1) projecting sign "union station"

Open the permit page

$10,000
Nov 24, 2021Completed
final sign-off Dec 2021
2075 Mission StIntegrity Air Systems Corporationrevised mechanical plans to 202009093749
Details
Permit
202111243113
Status
complete
Filed
Nov 24, 2021
Permit issued
Nov 30, 2021
Final sign-off
Dec 20, 2021
Address
2075 Mission St

revised mechanical plans to 202009093749

Open the permit page

Oct 20, 2021Completed
final sign-off Dec 2021
2075 Mission StSan Francisco Fire Protectionas-builts to pa 202103045881. delete 1 strobe on mezzanine, replace 4 wall mount strobes and 2 horn/strobes with ceiling mount at the same location. install new monitor modules to monitor 3 duct detectors.
Details
Permit
202110200858
Status
complete
Filed
Oct 20, 2021
Permit issued
Oct 20, 2021
Final sign-off
Dec 16, 2021
Declared cost
$2,000
Address
2075 Mission St

as-builts to pa 202103045881. delete 1 strobe on mezzanine, replace 4 wall mount strobes and 2 horn/strobes with ceiling mount at the same location. install new monitor modules to monitor 3 duct detectors.

Open the permit page

$2,000
Jun 28, 2021Never finaled
issued Jul 2021, no final
2075 Mission StAquamatic Fire Protectionrelocate 14 pendent heads, add 25 pendents and repl 8 heads for new walls being installed. total 47 heads. repl 70' of 1.5" to 2" pipe. install new 3" and 4" pipes to supply new heads.
Details
Permit
202106283350
Status
issued
Filed
Jun 28, 2021
Permit issued
Jul 13, 2021
Declared cost
$16,000
Address
2075 Mission St

relocate 14 pendent heads, add 25 pendents and repl 8 heads for new walls being installed. total 47 heads. repl 70' of 1.5" to 2" pipe. install new 3" and 4" pipes to supply new heads.

Open the permit page

$16,000
Mar 4, 2021Never finaled
issued Apr 2021, no final
2075 Mission StSan Francisco Fire Protectionadd on to existing fire alarm system due to new tenant on ground & mezzanine level. install new notification devices thru-out for complete coverage & tie-in to existing control panel on ground floor # 2017-0104-6470, # 2020-0909-3749
Details
Permit
202103045881
Status
issued
Filed
Mar 4, 2021
Permit issued
Apr 6, 2021
Declared cost
$5,000
Address
2075 Mission St

add on to existing fire alarm system due to new tenant on ground & mezzanine level. install new notification devices thru-out for complete coverage & tie-in to existing control panel on ground floor # 2017-0104-6470, # 2020-0909-3749

Open the permit page

$5,000
Nov 30, 2020Expired or cancelled
cancelled Nov 2024
2075 Mission StHasz Construction Incremove existing finishes. no structural. ab017.
Details
Permit
202011309862
Status
cancelled
Filed
Nov 30, 2020
Declared cost
$2,000
Address
2075 Mission St

remove existing finishes. no structural. ab017.

Open the permit page

$2,000
Nov 24, 2020Never finaled
filed Nov 2020, never issued
2075 Mission StGolden Gate Sign Company Inc.refurb/reface (e) signage. illuminated projecting double-faced blade sign. "union station"
Details
Permit
202011249604
Status
filed
Filed
Nov 24, 2020
Declared cost
$10,000
Address
2075 Mission St

refurb/reface (e) signage. illuminated projecting double-faced blade sign. "union station"

Open the permit page

$10,000
Sep 9, 2020Completed
final sign-off Dec 2021
2075 Mission StHasz Construction Incper cua 2019-004451prj tenant build out cannabis retail consumption lounge, mill work, storage, locker, shower rooms, office, existing restroom to be ada compliant, relocate doors at entry, new finishes, lighting.
Details
Permit
202009093749
Status
complete
Filed
Sep 9, 2020
Permit issued
Jun 17, 2021
Final sign-off
Dec 20, 2021
Declared cost
$420,000
Address
2075 Mission St

per cua 2019-004451prj tenant build out cannabis retail consumption lounge, mill work, storage, locker, shower rooms, office, existing restroom to be ada compliant, relocate doors at entry, new finishes, lighting.

Open the permit page

$420,000
May 12, 2017Never finaled
issued May 2017, no final
180 Capp StAquamatic Fire Protectionreplace 156 upright sprinklers and 9 pendnent sprinklers due to old sprinklers. upgrade eqrthquake bracing, and branch line restraints. no underground work. deficiency work only - no ti to reference
Details
Permit
201705126493
Status
issued
Filed
May 12, 2017
Permit issued
May 12, 2017
Declared cost
$16,000
Address
180 Capp St

replace 156 upright sprinklers and 9 pendnent sprinklers due to old sprinklers. upgrade eqrthquake bracing, and branch line restraints. no underground work. deficiency work only - no ti to reference

Open the permit page

$16,000
Jan 4, 2017Completed
final sign-off Aug 2017
180 Capp StSan Francisco Fire Protectionsprinkler water flow & supervisory system. install control panel, smoke detector, pull station & aes radio on ground floor. install monitor modules to tie-in existing water flow & tamper switches. ref pa 2016-110-2495
Details
Permit
201701046470
Status
complete
Filed
Jan 4, 2017
Permit issued
Jan 4, 2017
Final sign-off
Aug 8, 2017
Declared cost
$2,700
Address
180 Capp St

sprinkler water flow & supervisory system. install control panel, smoke detector, pull station & aes radio on ground floor. install monitor modules to tie-in existing water flow & tamper switches. ref pa 2016-110-2495

Open the permit page

$2,700
Nov 10, 2016Completed
final sign-off Sep 2018
180 Capp Stremoval of non-bearing walls at 3rd level only. no exterior work under this permit.
Details
Permit
201611102495
Status
complete
Filed
Nov 10, 2016
Permit issued
Nov 10, 2016
Final sign-off
Sep 25, 2018
Declared cost
$10,000
Address
180 Capp St

removal of non-bearing walls at 3rd level only. no exterior work under this permit.

Open the permit page

$10,000
Nov 20, 2013Never finaled
issued Nov 2013, no final
2073 Mission Stto obtain final inspection for work approved under pa# 200411129037. all work is complete.
Details
Permit
201311202452
Status
issued
Filed
Nov 20, 2013
Permit issued
Nov 20, 2013
Address
2073 Mission St

to obtain final inspection for work approved under pa# 200411129037. all work is complete.

Open the permit page

Nov 20, 2013Completed
final sign-off Jan 2014
2073 Mission Stto obtain final inspection for work approved under pa# 200504018921. all work is complete.
Details
Permit
201311202451
Status
complete
Filed
Nov 20, 2013
Permit issued
Nov 20, 2013
Final sign-off
Jan 21, 2014
Address
2073 Mission St

to obtain final inspection for work approved under pa# 200504018921. all work is complete.

Open the permit page

May 16, 2005Completed
final sign-off Nov 2013
2073 Mission Streviside coridor location at levels 2 & 3, revised use of office suits 202 & 302 with in b occupancy
Details
Permit
200505162503
Status
complete
Filed
May 16, 2005
Permit issued
May 16, 2005
Final sign-off
Nov 21, 2013
Address
2073 Mission St

reviside coridor location at levels 2 & 3, revised use of office suits 202 & 302 with in b occupancy

Open the permit page

Apr 1, 2005Expired or cancelled
expired Dec 2006
2073 Mission StJupiter Enterprises Incinstall ventilation systems for cosmotology school. mep. only
Details
Permit
200504018921
Status
expired
Filed
Apr 1, 2005
Permit issued
Apr 1, 2005
Declared cost
$1,000
Address
2073 Mission St

install ventilation systems for cosmotology school. mep. only

Open the permit page

$1,000
Feb 14, 2005Never finaled
issued Feb 2005, no final
2073 Mission Ststreetspace
Details
Permit
M31189
Status
issued
Filed
Feb 14, 2005
Permit issued
Feb 14, 2005
Address
2073 Mission St

streetspace

Open the permit page

Feb 1, 2005Completed
final sign-off May 2005
2073 Mission Strevised app#200411129037. 1st floor only.nc-3 personal service 712.89 ref.790.116 from maushel art&
Details
Permit
200502014518
Status
complete
Filed
Feb 1, 2005
Permit issued
Feb 1, 2005
Final sign-off
May 10, 2005
Address
2073 Mission St

revised app#200411129037. 1st floor only.nc-3 personal service 712.89 ref.790.116 from maushel art&

Open the permit page

Nov 12, 2004Expired or cancelled
expired Dec 2006
2073 Mission Stbarrier removal/new entry of mission st, toilets/new fire escape to be submitted separated per ab019
Details
Permit
200411129037
Status
expired
Filed
Nov 12, 2004
Permit issued
Dec 13, 2004
Declared cost
$80,000
Address
2073 Mission St

barrier removal/new entry of mission st, toilets/new fire escape to be submitted separated per ab019

Open the permit page

$80,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
San Francisco Fire Protection (3), Aquamatic Fire Protection (2), Golden Gate Sign Company Inc. (2), Hasz Construction Inc (2), Integrity Air Systems Corporation, Jupiter Enterprises Inc
Architects
Rony Rolnizky
Engineers
Kathryn Briggs, Mk Engineers Inc Steve H Kang

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.