Permits filed here

17 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Aug 25, 2026Completed
final sign-off Oct 2026
1813 15th StFrontside Constructionto address complaint #2025006321 enf: unit count restored to 6 units. 2 kitchens reinstalled per permit bpa #201808066527 to their original configuration. additional reconfigure kitchens in 1813 and 1815b and 1817b. englarge bathrooms to add a shower in units 1815b and 1817b
Details
Permit
202608257151
Permit issued
Sep 22, 2026
Final sign-off
Oct 22, 2026

to address complaint #2025006321 enf: unit count restored to 6 units. 2 kitchens reinstalled per permit bpa #201808066527 to their original configuration. additional reconfigure kitchens in 1813 and 1815b and 1817b. englarge bathrooms to add a shower in units 1815b and 1817b

Open the permit page

$40,000
Feb 26, 2020Never finaled
issued Feb 2020, no final
1813 15th Stper pa #201612286082, add address to new adu at block 3556, lot 048 as: 1813a 15th street.
Details
Permit
M1199408
Permit issued
Feb 26, 2020

per pa #201612286082, add address to new adu at block 3556, lot 048 as: 1813a 15th street.

Open the permit page

Oct 9, 2019Completed
final sign-off Nov 2019
1813 15th StCrime Watch Security Sys Llcinstallation of new sprinkler monitoring system. refer to pa 2019 0131 1769
Details
Permit
201910094019
Permit issued
Oct 9, 2019
Final sign-off
Nov 25, 2019

installation of new sprinkler monitoring system. refer to pa 2019 0131 1769

Open the permit page

$4,000
Oct 2, 2019Never finaled
issued Oct 2019, no final
1813 15th Ststreet space
Details
Permit
M1146827
Permit issued
Oct 2, 2019

street space

Open the permit page

Feb 5, 2019Never finaled
issued Feb 2019, no final
1813 15th Ststreet space
Details
Permit
M1035487
Permit issued
Feb 5, 2019

street space

Open the permit page

Jan 31, 2019Completed
final sign-off Nov 2019
1813 15th StJim Parr Dba Plumbinginstall (33) new sprinlers throughout; (20) in basement and (13) window sprinklers on level 1, 2, 3. underground per nfpa #24 ref pa 2016-1228-6082
Details
Permit
201901311769
Permit issued
Mar 11, 2019
Final sign-off
Nov 25, 2019

install (33) new sprinlers throughout; (20) in basement and (13) window sprinklers on level 1, 2, 3. underground per nfpa #24 ref pa 2016-1228-6082

Open the permit page

$10,000
Aug 23, 2018Completed
final sign-off Nov 2019
1813 15th StD K G Construction Incshoring
Details
Permit
201808238085
Permit issued
Aug 24, 2018
Final sign-off
Nov 20, 2019

shoring

Open the permit page

$50,000
Aug 6, 2018Completed
final sign-off Dec 2019
1813 15th StD K G Construction Increnovation of five apartments on levels 1,2,3. renovation of common areas and addition of extg passageway at basement level. new floor slab in basement. soft story under app#201803163943. adu under 201612286082
Details
Permit
201808066527
Permit issued
Sep 5, 2018
Final sign-off
Dec 3, 2019

renovation of five apartments on levels 1,2,3. renovation of common areas and addition of extg passageway at basement level. new floor slab in basement. soft story under app#201803163943. adu under 201612286082

Open the permit page

$200,000
Mar 27, 2018Never finaled
issued Mar 2018, no final
1813 15th Ststreet space
Details
Permit
M905388
Permit issued
Mar 27, 2018

street space

Open the permit page

Mar 16, 2018Completed
final sign-off Nov 2019
1813 15th StD K G Construction Incsoft story retrofit in accordance w/ sfebc chp 4d & 2016 cebc appendix a-4
Details
Permit
201803163943
Permit issued
Mar 23, 2018
Final sign-off
Nov 20, 2019

soft story retrofit in accordance w/ sfebc chp 4d & 2016 cebc appendix a-4

Open the permit page

$83,000
Dec 28, 2016Completed
final sign-off Dec 2019
1813 15th StD K G Construction Incadu per ord 162-16. convert garage to single dwelling unit. nfpa-13 sprinklers @ basement only. seismic retrofit under seperate permit #2016-1228-6019
Details
Permit
201612286082
Permit issued
Dec 19, 2018
Final sign-off
Dec 3, 2019

adu per ord 162-16. convert garage to single dwelling unit. nfpa-13 sprinklers @ basement only. seismic retrofit under seperate permit #2016-1228-6019

Open the permit page

$600,000
Dec 28, 2016Expired or cancelled
withdrawn Mar 2018
1813 15th Stsoft story stregtheniong to comply with sf mandatory program
Details
Permit
201612286019

soft story stregtheniong to comply with sf mandatory program

Open the permit page

$400,000
Jan 26, 2015Completed
final sign-off Jun 2015
1813 15th StArmstrong Installation Servicereroofing
Details
Permit
201501266711
Permit issued
Jan 26, 2015
Final sign-off
Jun 22, 2015

reroofing

Open the permit page

$15,800
May 14, 2012Never finaled
issued May 2012, no final
1813 15th Ststreet space permit.
Details
Permit
M320867
Permit issued
May 14, 2012

street space permit.

Open the permit page

Jan 12, 2005Never finaled
issued Jan 2005, no final
1813 15th Stsidewalk repair
Details
Permit
M30772
Permit issued
Jan 12, 2005

sidewalk repair

Open the permit page

Sep 18, 2002Completed
final sign-off Nov 2002
1813 15th Streplace existing rotten rear stairs (2nd egress) in kind per plan to respond complaint#200231834 &2
Details
Permit
200209186760
Permit issued
Sep 18, 2002
Final sign-off
Nov 1, 2002

replace existing rotten rear stairs (2nd egress) in kind per plan to respond complaint#200231834 &2

Open the permit page

$4,000
Aug 21, 2002Completed
final sign-off Nov 2002
1813 15th StWestern & Oriental Contractorrepair stairs less than 50% ti be repaired
Details
Permit
200208214510
Permit issued
Aug 21, 2002
Final sign-off
Nov 4, 2002

repair stairs less than 50% ti be repaired

Open the permit page

$6,500

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
D K G Construction Inc (4), Armstrong Installation Service, Crime Watch Security Sys Llc, Frontside Construction, Jim Parr Dba Plumbing, Western & Oriental Contractor
Architects
Benjamin Farrell, Mark Hogan
Engineers
Erwin O'toole, Kelly Turbin, M.L. Hicks, Mark Hogan

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover apartment buildings like this one.