Block 2656, lot 036
233 Corbett Ave
- City’s use
- Multi-Family Residential
- Built
- 1900
- Stories
- 3
- Units
- 2
- Rooms
- 4 bedrooms, 4 bathrooms
- Building
- 2,784 sq ft
- Lot
- 1,886 sq ft
- Zoning
- RH2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
22 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 17, 2026 | In progress issued Sep 2026 | 233 Corbett Av | Umlaut Interiors Llc | relace dry rot rear decks in-kind, replace wood railings with new cable railingsDetails
relace dry rot rear decks in-kind, replace wood railings with new cable railings | $45,000 |
| Mar 5, 2020 | Never finaled issued Mar 2020, no final | 235 Corbett Av | Pop Construction A Parnership | street spaceDetails
street space | |
| Jan 2, 2020 | Never finaled issued Jan 2020, no final | 235 Corbett Av | street spaceDetails
street space | ||
| Oct 18, 2019 | Never finaled issued Oct 2019, no final | 235 Corbett Av | street space onlyDetails
street space only | ||
| Sep 26, 2019 | Completed final sign-off Dec 2021 | 235 Corbett Av | Pop Construction A Parnership | provide revision to 201907236599 revision includes modification to skylights at roof levelDetails
provide revision to 201907236599 revision includes modification to skylights at roof level | $1,000 |
| Sep 25, 2019 | Completed final sign-off Mar 2020 | 235 Corbett Av | Pop Construction A Parnership | reroofingDetails
reroofing | $5,000 |
| Aug 8, 2019 | Never finaled issued Aug 2019, no final | 235 Corbett Av | street spaceDetails
street space | ||
| Aug 5, 2019 | Completed final sign-off Mar 2020 | 235 Corbett Av | Pop Construction A Parnership | 40% in kind roof replacement in the back due to dry rot and complete back exterior wall in kind replacement due to dry rotDetails
40% in kind roof replacement in the back due to dry rot and complete back exterior wall in kind replacement due to dry rot | $40,000 |
| Jul 23, 2019 | Completed final sign-off Dec 2021 | 233 Corbett Av | Pop Construction A Parnership | provide roof improvements at subject building including: new roof-mounted hvac equipment, in-kind replacement of 2 (e) skylights and 2 (n) skylights, install new rafters for roof structural reinforcement.Details
provide roof improvements at subject building including: new roof-mounted hvac equipment, in-kind replacement of 2 (e) skylights and 2 (n) skylights, install new rafters for roof structural reinforcement. | $35,000 |
| May 1, 2019 | Never finaled issued May 2019, no final | 235 Corbett Av | street spaceDetails
street space | ||
| Mar 28, 2019 | Completed final sign-off Dec 2021 | 235 Corbett Av | Pop Construction A Parnership | upper unit remodel kitchen and bath. add 2nd bath, replace windows & doors not visible to street. reframe ceiling joists if necssary. general mep upgradesDetails
upper unit remodel kitchen and bath. add 2nd bath, replace windows & doors not visible to street. reframe ceiling joists if necssary. general mep upgrades | $59,000 |
| Dec 3, 2018 | Completed final sign-off Mar 2019 | 233 Corbett Av | Pop Construction A Parnership | in-kind remodel of bathroom in street level story including removing existing bathtub and replacing it with new walk-in shower. also includes upgrading existing fixtures, cabinets, toilet, and sink.Details
in-kind remodel of bathroom in street level story including removing existing bathtub and replacing it with new walk-in shower. also includes upgrading existing fixtures, cabinets, toilet, and sink. | $20,000 |
| Jun 21, 2017 | Completed final sign-off Jul 2017 | 233 Corbett Av | revision to #201412163786, inspector instructed plans to match field condition before final. no changes visble from street. no room changes. footprint the same. main fl: straighten stairs, remove bedrm wall but leave beams, switch rear window w/patio door. lower fl: straighten stairs, switch bath w/Details
revision to #201412163786, inspector instructed plans to match field condition before final. no changes visble from street. no room changes. footprint the same. main fl: straighten stairs, remove bedrm wall but leave beams, switch rear window w/patio door. lower fl: straighten stairs, switch bath w/ | ||
| Jun 12, 2015 | Completed final sign-off May 2016 | 233 Corbett Av | Rafael Miranda Dba R M Constr. | project under construction. respond to nov dated 5/20/15 #201549572. provide reinforcement to 72 lf of extg foundation beyond original . scope of work provide temporary shoring.Details
project under construction. respond to nov dated 5/20/15 #201549572. provide reinforcement to 72 lf of extg foundation beyond original . scope of work provide temporary shoring. | $7,200 |
| Dec 16, 2014 | Completed final sign-off Jul 2017 | 233 Corbett Av | Rafael Miranda Dba R M Constr. | reconfigure new interior stair between main(street)level & lower flr & to basement. remodel lower flr rumpus room,laundry,bedrm,&bath.capture (e)covered porch areas for habitable space.patio & window changes not visible from street.partial basement to have "lanai"indoor/outdoor non condition space.Details
reconfigure new interior stair between main(street)level & lower flr & to basement. remodel lower flr rumpus room,laundry,bedrm,&bath.capture (e)covered porch areas for habitable space.patio & window changes not visible from street.partial basement to have "lanai"indoor/outdoor non condition space. | $140,687 |
| Aug 18, 2014 | Never finaled issued Aug 2014, no final | 233 Corbett Av | Rafael Miranda Dba R M Constr. | replace five windows at the front with aluminum clad wood double hung windows.Details
replace five windows at the front with aluminum clad wood double hung windows. | $3,500 |
| Feb 16, 2012 | Never finaled issued Feb 2012, no final | 233 Corbett Av | Rafael Miranda Dba R M Constr. | relocate electrical sub panel in upper residential unit from closet to living room, add hose bib faucet at rear deckDetails
relocate electrical sub panel in upper residential unit from closet to living room, add hose bib faucet at rear deck | $5,000 |
| Sep 13, 2010 | Never finaled issued Sep 2010, no final | 233 Corbett Av | Nelson Contracting | bath room remodel on the housekeeping unit # 233a. no wall removal, work on housingkeeping area 233aDetails
bath room remodel on the housekeeping unit # 233a. no wall removal, work on housingkeeping area 233a | $5,000 |
| Apr 17, 2006 | Completed final sign-off Sep 2006 | 233 Corbett Av | Nbt Construction | replace sliding glass door & 2 windows in back (no change to size). replace kitchen cabinets & appliances. (no changes to partition or windows). add washer dryer. fluor. lights only in kitchen. replace bathroom fixtures. paint.Details
replace sliding glass door & 2 windows in back (no change to size). replace kitchen cabinets & appliances. (no changes to partition or windows). add washer dryer. fluor. lights only in kitchen. replace bathroom fixtures. paint. | $40,000 |
| Feb 6, 2004 | Completed final sign-off Oct 2004 | 233 Corbett Av | comply with notice of violation. correct the record to show existing use of two family dwelling plusDetails
comply with notice of violation. correct the record to show existing use of two family dwelling plus | ||
| May 15, 2003 | Completed final sign-off Nov 2003 | 233 Corbett Av | minor kitchen remodel and repairs in first unit, no structuralDetails
minor kitchen remodel and repairs in first unit, no structural | $2,500 | |
| May 26, 2000 | Expired or cancelled expired Sep 2000 | 235 Corbett Av | S'top Home Service Roofing Co. Inc. | reroofingDetails
reroofing | $4,280 |
Find contractors for work like this