Block 2055, lot 043

1890 19th Ave

City’s use
Commercial Misc
Built
1964
Stories
1
Units
1
Rooms
2 bathrooms
Building
1,100 sq ft
Lot
10,249 sq ft
Zoning
NC1
Construction type
S

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

6 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jun 9, 2026In progress
issued Jun 2026
1890 19th AvCgrs Incinstall 2 (n) containment solutions fiberglass (csi) 12000 gallons ust's- 1-1200gal for 87 products and 1-12000gal for 890 product and split tank for 2x6k gal tanks for 91 product and 6k for diseasel. pre install (e) four (4) dispose. install (n) nov double wall piping, ancillary equipment finaltest
Details
Permit
202606092870
Status
issued
Filed
Jun 9, 2026
Permit issued
Jun 29, 2026
Declared cost
$1,200,000
Address
1890 19th Av

install 2 (n) containment solutions fiberglass (csi) 12000 gallons ust's- 1-1200gal for 87 products and 1-12000gal for 890 product and split tank for 2x6k gal tanks for 91 product and 6k for diseasel. pre install (e) four (4) dispose. install (n) nov double wall piping, ancillary equipment finaltest

Open the permit page

$1,200,000
Jun 16, 2017Completed
final sign-off Jan 2018
1890 19th AvArmer/Norman & Associates, Able Maintenance Increplace gasoline dispensers, install bravo conversion frame, convert contensts of tank #3 from 89 to 87 octane, upgrade isd software reinstall existing nozzles and hoses. n/a for maher ordinance.
Details
Permit
201706169533
Status
complete
Filed
Jun 16, 2017
Permit issued
Jan 10, 2018
Final sign-off
Jan 22, 2018
Declared cost
$109,000
Address
1890 19th Av

replace gasoline dispensers, install bravo conversion frame, convert contensts of tank #3 from 89 to 87 octane, upgrade isd software reinstall existing nozzles and hoses. n/a for maher ordinance.

Open the permit page

$109,000
Mar 25, 2010Never finaled
issued Mar 2010, no final
1890 19th Avstreet and sidewalk permits
Details
Permit
M194726
Status
issued
Filed
Mar 25, 2010
Permit issued
Mar 25, 2010
Address
1890 19th Av

street and sidewalk permits

Open the permit page

Sep 24, 2009Never finaled
issued Oct 2009, no final
1890 19th AvGettler-Ryan Increvision to 200806245158: install veeder root carbon cannister in lieu of healy clean air separator
Details
Permit
200909247630
Status
issued
Filed
Sep 24, 2009
Permit issued
Oct 6, 2009
Address
1890 19th Av

revision to 200806245158: install veeder root carbon cannister in lieu of healy clean air separator

Open the permit page

Jun 24, 2008Never finaled
issued Jun 2008, no final
1890 19th AvGettler-Ryan Incenhanced vapor recovery phase ii upgrade. install new healy clean air separator on a concrete pad.
Details
Permit
200806245158
Status
issued
Filed
Jun 24, 2008
Permit issued
Jun 24, 2008
Declared cost
$25,000
Address
1890 19th Av

enhanced vapor recovery phase ii upgrade. install new healy clean air separator on a concrete pad.

Open the permit page

$25,000
May 13, 2008Completed
final sign-off Dec 2008
1890 19th AvJohnson United Inc Dba United Sign Systeerect electric, wall, double faced sign.
Details
Permit
200805131903
Status
complete
Filed
May 13, 2008
Permit issued
May 13, 2008
Final sign-off
Dec 8, 2008
Declared cost
$2,500
Address
1890 19th Av

erect electric, wall, double faced sign.

Open the permit page

$2,500