Permit GraphShortlistSan Francisco building permits since 2000

Block 1752, lot 009

1289 03rd Ave

City’s use
Multi-Family Residential
Built
1907
Stories
2
Units
3
Rooms
5 bedrooms, 4 bathrooms
Building
3,416 sq ft
Lot
2,374 sq ft
Zoning
RH2
Construction type
NA

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

8 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Feb 6, 2025Completed
final sign-off May 2025
1289 03rd AvPuzzlewood Buildersold cabinat removed and new one installed to match existing.
Details
Permit
202502069819
Status
complete
Filed
Feb 6, 2025
Permit issued
Feb 6, 2025
Final sign-off
May 9, 2025
Declared cost
$27,000
Address
1289 03rd Av

old cabinat removed and new one installed to match existing.

Open the permit page

$27,000
May 24, 2023Completed
final sign-off Jun 2023
1287 03rd AvThe Toboni Groupreplace furnace. demo drywall at 15' of ceiling, and repair drywall after work, repair ducting for furnace. remove abandoned interior/ disconnected water pipe. same location as previous. less than 25 ft of new ductwork
Details
Permit
202305248489
Status
complete
Filed
May 24, 2023
Permit issued
May 26, 2023
Final sign-off
Jun 16, 2023
Declared cost
$5,000
Address
1287 03rd Av

replace furnace. demo drywall at 15' of ceiling, and repair drywall after work, repair ducting for furnace. remove abandoned interior/ disconnected water pipe. same location as previous. less than 25 ft of new ductwork

Open the permit page

$5,000
May 15, 2023Completed
final sign-off May 2023
1291 03rd AvThe Toboni Grouprevision to clarify scope of pa# 202304105385: ground floor until 1291 bath remodel in kind only. 1289 second floor bathroom remodel, replace plumbing fixtures and new lighting. no kitchen work anywhere.
Details
Permit
202305157783
Status
complete
Filed
May 15, 2023
Permit issued
May 15, 2023
Final sign-off
May 22, 2023
Address
1291 03rd Av

revision to clarify scope of pa# 202304105385: ground floor until 1291 bath remodel in kind only. 1289 second floor bathroom remodel, replace plumbing fixtures and new lighting. no kitchen work anywhere.

Open the permit page

Apr 10, 2023Completed
final sign-off May 2023
1291 03rd AvThe Toboni Group1st floor bathroom remodel- 2nd floor fixtures replacement. kitchen and bathroom remodel. no structural work.
Details
Permit
202304105385
Status
complete
Filed
Apr 10, 2023
Permit issued
Apr 10, 2023
Final sign-off
May 22, 2023
Declared cost
$2,500
Address
1291 03rd Av

1st floor bathroom remodel- 2nd floor fixtures replacement. kitchen and bathroom remodel. no structural work.

Open the permit page

$2,500
Aug 31, 2022Completed
final sign-off Sep 2022
1287 03rd AvHighland Construction S F Inc.reroofing
Details
Permit
202208311628
Status
complete
Filed
Aug 31, 2022
Permit issued
Aug 31, 2022
Final sign-off
Sep 7, 2022
Declared cost
$9,800
Address
1287 03rd Av

reroofing

Open the permit page

$9,800
Mar 30, 2009Completed
final sign-off Dec 2009
1287 03rd Avadd new foundation, posts and beams in the middle at the ground floor. replace teh (e) posts and beams as shown on plans.
Details
Permit
200903305162
Status
complete
Filed
Mar 30, 2009
Permit issued
Mar 30, 2009
Final sign-off
Dec 9, 2009
Declared cost
$6,000
Address
1287 03rd Av

add new foundation, posts and beams in the middle at the ground floor. replace teh (e) posts and beams as shown on plans.

Open the permit page

$6,000
Nov 20, 2008Completed
final sign-off Dec 2009
1287 03rd Avdry rot repair of 10' section of the south exterior wall by raising the foundation (min 12") with reinforced concrete & install new sill. voluntary to improve horizontal resistance of the ground floor by installing a steel beam & column system
Details
Permit
200811207012
Status
complete
Filed
Nov 20, 2008
Permit issued
Nov 26, 2008
Final sign-off
Dec 9, 2009
Declared cost
$10,000
Address
1287 03rd Av

dry rot repair of 10' section of the south exterior wall by raising the foundation (min 12") with reinforced concrete & install new sill. voluntary to improve horizontal resistance of the ground floor by installing a steel beam & column system

Open the permit page

$10,000
Sep 21, 2007Completed
final sign-off Nov 2008
1287 03rd Avcombine ex. unit 1287a and 1287b on the 3rd floor level into one unit (unit 1287). this will reduce the number of units in this bldg from 4 to 3. the ex. kitchen in unit 1287a will be converted into study rm. and laundry rm. complaint nov 200557388.
Details
Permit
200709213293
Status
complete
Filed
Sep 21, 2007
Permit issued
Oct 31, 2008
Final sign-off
Nov 7, 2008
Declared cost
$2,000
Address
1287 03rd Av

combine ex. unit 1287a and 1287b on the 3rd floor level into one unit (unit 1287). this will reduce the number of units in this bldg from 4 to 3. the ex. kitchen in unit 1287a will be converted into study rm. and laundry rm. complaint nov 200557388.

Open the permit page

$2,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
The Toboni Group (3), Highland Construction S F Inc., Puzzlewood Builders
Engineers
John Lau

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover apartment buildings like this one.