| Sep 1, 2015 | Completed final sign-off Dec 2015 | 607 02nd Av | Huff Construction Company Inc | to comply with physical inspection report #cc-7923Details
to comply with physical inspection report #cc-7923 | $500 |
| Sep 1, 2015 | Never finaled issued Sep 2015, no final | 607 02nd Av | Huff Construction Company Inc | renew of pa# 201010203441. to obtain final inspection for work approved under pa# 201010203441. all work is complete.Details
renew of pa# 201010203441. to obtain final inspection for work approved under pa# 201010203441. all work is complete. | |
| Aug 20, 2015 | Never finaled issued Aug 2015, no final | 607 02nd Av | Huff Construction Company Inc | install barrier at water heater in garage - steel bollard.Details
install barrier at water heater in garage - steel bollard. | $300 |
| Apr 15, 2014 | Never finaled issued Apr 2014, no final | 607 02nd Av | to obtain final inspection for work approved under pa 201010203441; allwork is completeDetails
to obtain final inspection for work approved under pa 201010203441; allwork is complete | ||
| Feb 22, 2011 | Completed final sign-off Dec 2011 | 607 02nd Av | Aaa Restaurant Fire Control/Dba Aaa Fire | installation of underground piping for fire service- sprinklers under separate permit- 201010203441- bfp above groundDetails
installation of underground piping for fire service- sprinklers under separate permit- 201010203441- bfp above ground | $2,400 |
| Dec 10, 2010 | Never finaled issued Dec 2010, no final | 607 02nd Av | street space & sidewalkDetails
street space & sidewalk | ||
| Oct 20, 2010 | Never finaled issued Oct 2010, no final | 607 02nd Av | Aaa Restaurant Fire Control/Dba Aaa Fire | complete installation of new sprinkler system ( 61 heads total ). 2" underground line/connection and combination meter under separate permitDetails
complete installation of new sprinkler system ( 61 heads total ). 2" underground line/connection and combination meter under separate permit | $25,000 |
| Feb 8, 2010 | Completed final sign-off Dec 2011 | 607 02nd Av | Leonard Schendel Const.Co | comply w/nov# 200927862.renovate(e)2 stories over garage.each a sep unit.reconf kitchen,bath&living/storage space.at lower unit,add a add'l fl area&deck w/stair to grade.at upper unit,add add'l level w/int stair.new bedrm,bath,living&storage areas to top fl.add sprk sys to whl bldg under sep appl.Details
comply w/nov# 200927862.renovate(e)2 stories over garage.each a sep unit.reconf kitchen,bath&living/storage space.at lower unit,add a add'l fl area&deck w/stair to grade.at upper unit,add add'l level w/int stair.new bedrm,bath,living&storage areas to top fl.add sprk sys to whl bldg under sep appl. | $110,000 |
| Oct 2, 2009 | Never finaled issued Oct 2009, no final | 607 02nd Av | street space permit.Details
street space permit. | ||
| Sep 28, 2009 | Expired or cancelled cancelled Nov 2010 | 607 02nd Av | remodel level 2 & 3 per plans, remodel level 3 bathroom, new plubming level 2 & 3 in bathrooms, turn stairs level 3, new laundry in level 3, perform 3r-4909 fixtures, replace (e) bathroom in garage, new electrical in level 2 & 3, replace all windows; rev to pa#200904247067.Details
remodel level 2 & 3 per plans, remodel level 3 bathroom, new plubming level 2 & 3 in bathrooms, turn stairs level 3, new laundry in level 3, perform 3r-4909 fixtures, replace (e) bathroom in garage, new electrical in level 2 & 3, replace all windows; rev to pa#200904247067. | $35,000 | |
| Aug 26, 2009 | Never finaled issued Aug 2009, no final | 607 02nd Av | street space permit only.Details
street space permit only. | ||
| Apr 24, 2009 | Expired or cancelled cancelled Nov 2010 | 607 02nd Av | widen garage, add new beam in garage,fire proff garage, new heating system, comply with bldg codes. new electrical and plumbing. on 3r-4909. general bldg items 1-3, 609 lower items 4 & 5, 607 (upper) item 6. replace 2 bearing walls in garage with new beam + post.Details
widen garage, add new beam in garage,fire proff garage, new heating system, comply with bldg codes. new electrical and plumbing. on 3r-4909. general bldg items 1-3, 609 lower items 4 & 5, 607 (upper) item 6. replace 2 bearing walls in garage with new beam + post. | $30,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Huff Construction Company Inc (3), Aaa Restaurant Fire Control/Dba Aaa Fire (2), Leonard Schendel Const.Co
- Architects
- Ryan Francis Knock
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.