Block 1341, lot 025
25 17th Ave
- City’s use
- Single Family Residential
- Built
- 1913
- Stories
- 2
- Rooms
- 5 bedrooms, 4 bathrooms
- Building
- 3,564 sq ft
- Lot
- 3,000 sq ft
- Zoning
- NA
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
12 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 21, 2023 | Never finaled issued Apr 2023, no final | 25 17th Av | Fong's Construction & Plumbing | as-built fire sprinklers, ref pa # 202103116441.Details
as-built fire sprinklers, ref pa # 202103116441. | |
| Jul 8, 2022 | Completed final sign-off Jul 2023 | 25 17th Av | Crime Watch Security Sys Llc | installation of new sprinkler monitoring system. ref sprinkler pa# 202103116441.Details
installation of new sprinkler monitoring system. ref sprinkler pa# 202103116441. | $4,000 |
| Apr 7, 2022 | Completed final sign-off Mar 2024 | 25 17th Av | pay increased permit fees on pa# 201707071206. job value is 600,000. original permit was 575,000. scope of work was revised and value should have been increased to 600,000 before issurance.Details
pay increased permit fees on pa# 201707071206. job value is 600,000. original permit was 575,000. scope of work was revised and value should have been increased to 600,000 before issurance. | $25,000 | |
| Nov 22, 2021 | Completed final sign-off Mar 2024 | 25 17th Av | revision to previously approved pa# 201712136333 & subsequent pa# 201707071206. a) memorialize the transition of the foundation system,b) revise beam size & replace simpson frames w/ special moment frames below 3/f. c)confirm arch revision approved under pa# 202109299421 had no structural impactDetails
revision to previously approved pa# 201712136333 & subsequent pa# 201707071206. a) memorialize the transition of the foundation system,b) revise beam size & replace simpson frames w/ special moment frames below 3/f. c)confirm arch revision approved under pa# 202109299421 had no structural impact | ||
| Sep 29, 2021 | Completed final sign-off Mar 2024 | 25 17th Av | revision to app#201707071206: reduce size of sliding glass door at rear first floor 16' to 13' 6"(reduce glazing from 128 sq ft to 121.5 sq ft) and reduce size of sliding glass door at rear. 2nd floor from 16' to 13' 6"(reduce glazing from 128 sq ft to 114.75 sq ft)Details
revision to app#201707071206: reduce size of sliding glass door at rear first floor 16' to 13' 6"(reduce glazing from 128 sq ft to 121.5 sq ft) and reduce size of sliding glass door at rear. 2nd floor from 16' to 13' 6"(reduce glazing from 128 sq ft to 114.75 sq ft) | ||
| Aug 13, 2021 | Completed final sign-off Mar 2024 | 25 17th Av | An Dun Construction | rev to pa201712136333 & 201707071206:new foundations at steel columns rev to beam sizes and replace simpson fream with special moment frame below 3/f. no arch changes.Details
rev to pa201712136333 & 201707071206:new foundations at steel columns rev to beam sizes and replace simpson fream with special moment frame below 3/f. no arch changes. | |
| Mar 11, 2021 | Never finaled issued May 2021, no final | 25 17th Av | Fong's Construction & Plumbing | install new fire sprinkler system throughout building per nfpa 13-r including 2" dedicated fire service. (total sprinklers 60) ref # 2017-0707-1206Details
install new fire sprinkler system throughout building per nfpa 13-r including 2" dedicated fire service. (total sprinklers 60) ref # 2017-0707-1206 | $33,000 |
| Jun 19, 2018 | Completed final sign-off Jun 2018 | 25 17th Av | An Dun Construction | to obtain final inspection for work approved under pa#20160701417. all work is complete.Details
to obtain final inspection for work approved under pa#20160701417. all work is complete. | |
| Dec 13, 2017 | Completed final sign-off Mar 2024 | 25 17th Av | An Dun Construction | per bpa decision for apeal #17-128: ground floor lateral & vertical upgrade - interior work only. no work to occur above the finished floor of 2nd floor. removal of (e) elements ( ref enf 2016-009806 & nov #201623795 & #2017-57399) addressed under separate permit for each lot.Details
per bpa decision for apeal #17-128: ground floor lateral & vertical upgrade - interior work only. no work to occur above the finished floor of 2nd floor. removal of (e) elements ( ref enf 2016-009806 & nov #201623795 & #2017-57399) addressed under separate permit for each lot. | $100,000 |
| Aug 30, 2017 | Completed final sign-off Sep 2017 | 25 17th Av | An Dun Construction | comply with nov# 201700172, corrections (1) berming of undermine foundation w/compacted soil, (2) cross bracing at every story in transverse direction,(3) positive connection between cribbing towers & shoring beams,(4) plywood sheathing of cribbing towers.Details
comply with nov# 201700172, corrections (1) berming of undermine foundation w/compacted soil, (2) cross bracing at every story in transverse direction,(3) positive connection between cribbing towers & shoring beams,(4) plywood sheathing of cribbing towers. | $2,500 |
| Jul 7, 2017 | Completed final sign-off Mar 2024 | 25 17th Av | An Dun Construction | to comply w/ nov 201623795 & 201757399 & plann enf case #2016009806, horzon additn, lobby elevator, entertait rm, bath at 1st fl, laundry, 3 bath 2nd & 3rd fl, replace side walk, repair stucco, relocate meter, reppair fence, add 1 bedrm & bath at 4th floor. no penalty for this 201707171206Details
to comply w/ nov 201623795 & 201757399 & plann enf case #2016009806, horzon additn, lobby elevator, entertait rm, bath at 1st fl, laundry, 3 bath 2nd & 3rd fl, replace side walk, repair stucco, relocate meter, reppair fence, add 1 bedrm & bath at 4th floor. no penalty for this 201707171206 | $300,000 |
| May 18, 2017 | Completed final sign-off Mar 2024 | 25 17th Av | An Dun Construction | abate planning 2016-009806 enf, abate dbi nov#201623795 �. remove exterior bay and chase along south wall at all floors. interior remodel at ground floor. at ground fl & 2nd fl: voluntary lateral strengthening & partial structural strengthening of floor. removal of exterior deck & stairs.Details
abate planning 2016-009806 enf, abate dbi nov#201623795 �. remove exterior bay and chase along south wall at all floors. interior remodel at ground floor. at ground fl & 2nd fl: voluntary lateral strengthening & partial structural strengthening of floor. removal of exterior deck & stairs. | $100,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- An Dun Construction (6), Fong's Construction & Plumbing (2), Crime Watch Security Sys Llc
- Architects
- Yang Nie (2)
- Engineers
- Rodrigo Santos (2), Albert Urrutia
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover single-family homes like this one.