Block 1205, lot 023
340 Baker St
- City’s use
- Multi-Family Residential
- Built
- 1960
- Stories
- 2
- Units
- 9
- Rooms
- 12 bedrooms, 9 bathrooms
- Building
- 8,368 sq ft
- Lot
- 4,996 sq ft
- Zoning
- RM1
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
12 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 31, 2024 | Completed final sign-off Sep 2024 | 340 Baker St | Crime Watch Security Sys Llc | upgrade existing fire alarm system to comply with sffc section 1103.7.6.1Details
upgrade existing fire alarm system to comply with sffc section 1103.7.6.1 | $27,480 |
| Feb 12, 2021 | Completed final sign-off May 2022 | 340 Baker St | Alef Construction Corp | apt #6: to relocate (e) kitchen & bathroom (on 2nd fl). new electrical & plumbing. no fire sprinkler system.Details
apt #6: to relocate (e) kitchen & bathroom (on 2nd fl). new electrical & plumbing. no fire sprinkler system. | $40,000 |
| Dec 31, 2020 | Completed final sign-off Jun 2022 | 340 Baker St | Alef Construction Corp | apt# 8: remodel (e) kitchen & bathroom, new lighting in common areas (e) hallways, new elec, ligting & plumbing only in apt. 8 and hallways, no work performed in other areas, building does not have a fire sprinkler systemDetails
apt# 8: remodel (e) kitchen & bathroom, new lighting in common areas (e) hallways, new elec, ligting & plumbing only in apt. 8 and hallways, no work performed in other areas, building does not have a fire sprinkler system | $50,000 |
| Nov 21, 2016 | Completed final sign-off Sep 2017 | 340 Baker St | Alef Construction Corp | revise permit #201605258235. wall removed in permit #201605258235 required structural support. 4 6x6 post were added along with an "i" beam. the scope of the project remaining same as permit #201605258235.Details
revise permit #201605258235. wall removed in permit #201605258235 required structural support. 4 6x6 post were added along with an "i" beam. the scope of the project remaining same as permit #201605258235. | $2,500 |
| Aug 18, 2016 | Completed final sign-off Sep 2017 | 340 Baker St | Alef Construction Corp | seismic retrofit of first floor new shearwalls to be installed with shearwall holddowns installed with epoxy anchorage. new hardy frame shear panels to be installed with a new concrete pad foundation at eache hardy frame. appdx a4.Details
seismic retrofit of first floor new shearwalls to be installed with shearwall holddowns installed with epoxy anchorage. new hardy frame shear panels to be installed with a new concrete pad foundation at eache hardy frame. appdx a4. | $35,000 |
| May 25, 2016 | Completed final sign-off Sep 2017 | 340 Baker St | Alef Construction Corp | 1st floor: move laundry room to a remodeled space & create a storage room for building supplies. (e) corridor will be reduced to make room for (n) cage storage lockers to be installed per manufacture.bike rack installed. (n) electrical & lighting.Details
1st floor: move laundry room to a remodeled space & create a storage room for building supplies. (e) corridor will be reduced to make room for (n) cage storage lockers to be installed per manufacture.bike rack installed. (n) electrical & lighting. | $25,000 |
| Aug 20, 2015 | Completed final sign-off Sep 2015 | 340 Baker St | Alef Construction Corp | 3rd flr, unit 7: remodel unit an (e) non bearing wall removed to create an open plan. (n) plan will have 1 bedrm, 1 bathrom, an ofc, kitchen, living rm, dining rm & hall closet. (n) elect, plumb, insulation will be installed. all wood rot will be repairDetails
3rd flr, unit 7: remodel unit an (e) non bearing wall removed to create an open plan. (n) plan will have 1 bedrm, 1 bathrom, an ofc, kitchen, living rm, dining rm & hall closet. (n) elect, plumb, insulation will be installed. all wood rot will be repair | $40,000 |
| Apr 29, 2015 | Completed final sign-off Aug 2015 | 340 Baker St | Alef Construction Corp | 2nd floor in unit #2,3,& 5: an extg non-bearing wall will be removed to create open floor plan. the new plan will have one bedroom, 1 bathroom, an office, kitchen, living rm, dining room, & hall closet. new elect., & plmbg, insulate wall & replace wood rot.Details
2nd floor in unit #2,3,& 5: an extg non-bearing wall will be removed to create open floor plan. the new plan will have one bedroom, 1 bathroom, an office, kitchen, living rm, dining room, & hall closet. new elect., & plmbg, insulate wall & replace wood rot. | $150,000 |
| Jul 14, 2014 | Never finaled issued Feb 2015, no final | 340 Baker St | Alef Construction Corp | apt #4: install one support beam below apt #4, and concrete footing.Details
apt #4: install one support beam below apt #4, and concrete footing. | $2,300 |
| Apr 22, 2014 | Completed final sign-off Jul 2014 | 340 Baker St | Graham Moore Construction Inc | remodel unit 4. new kitchen cabinets, appliances, remodel bathroom. add interior walls and doorsDetails
remodel unit 4. new kitchen cabinets, appliances, remodel bathroom. add interior walls and doors | $30,000 |
| Jun 13, 2013 | Never finaled issued Jun 2013, no final | 340 Baker St | replace cabinet, wood floor, bath tub, vanity, tile, paint. convert closet into waher and dryer. new lights, plugs and switches.Details
replace cabinet, wood floor, bath tub, vanity, tile, paint. convert closet into waher and dryer. new lights, plugs and switches. | $30,000 | |
| Dec 2, 2009 | Completed final sign-off Dec 2009 | 340 Baker St | A -1 Roof Management & Construction, Inc | reroofingDetails
reroofing | $16,300 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Alef Construction Corp (8), A -1 Roof Management & Construction, Inc, Crime Watch Security Sys Llc, Graham Moore Construction Inc
- Architects
- Maxwell Beaumont (3)
- Engineers
- W.L. Hicks
Find contractors for work like this