Block 0975, lot 003
2201 Baker St
- City’s use
- Multi-Family Residential
- Built
- 1904
- Stories
- 3
- Units
- 2
- Rooms
- 7 bathrooms
- Building
- 5,240 sq ft
- Lot
- 3,705 sq ft
- Zoning
- RH3
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
28 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 20, 2020 | Never finaled issued May 2020, no final | 2201 Baker St | street space | ||
| Oct 7, 2019 | Completed final sign-off Feb 2021 | 2201 Baker St | Cairn Construction | remodel of (e) entry level including associated structural work. bath remodel and new stair connecting 1-4th levels. new steel door at 2nd levelDetails
remodel of (e) entry level including associated structural work. bath remodel and new stair connecting 1-4th levels. new steel door at 2nd level | $150,000 |
| May 16, 2017 | Never finaled issued May 2017, no final | 2201 Baker St | street space permit | ||
| Aug 4, 2014 | Never finaled issued Aug 2014, no final | 2201 Baker St | street space | ||
| Aug 19, 2009 | Completed final sign-off Aug 2009 | 2201 Baker St | to complete and obtain final inspection for work approved under pa 200802064121; all work has been completed; sp insp reqdDetails
to complete and obtain final inspection for work approved under pa 200802064121; all work has been completed; sp insp reqd | ||
| Aug 19, 2009 | Expired or cancelled cancelled Nov 2009 | 2201 Baker St | to obtain final inspection for work approved under pa 200812047794; all work has been completedDetails
to obtain final inspection for work approved under pa 200812047794; all work has been completed | ||
| Aug 19, 2009 | Never finaled issued Aug 2009, no final | 2201 Baker St | to obtain final inspection for work approved under pa 200806275593; all work has been completed.Details
to obtain final inspection for work approved under pa 200806275593; all work has been completed. | ||
| Aug 19, 2009 | Never finaled issued Aug 2009, no final | 2201 Baker St | to obtain final inspection for work approved under pa 200803066540; sp insp requiredDetails
to obtain final inspection for work approved under pa 200803066540; sp insp required | ||
| Aug 19, 2009 | Never finaled issued Aug 2009, no final | 2201 Baker St | to obtain final inspection for work approved under pa 200804149657; all work has been completed.Details
to obtain final inspection for work approved under pa 200804149657; all work has been completed. | ||
| Aug 19, 2009 | Completed final sign-off Aug 2009 | 2201 Baker St | to obtain final inspection for work approved under pa 200810083709; all work has been completedDetails
to obtain final inspection for work approved under pa 200810083709; all work has been completed | ||
| Aug 19, 2009 | Expired or cancelled cancelled Nov 2009 | 2201 Baker St | to obtain final inspection for work approved under pa 200601031370; sp insp requiredDetails
to obtain final inspection for work approved under pa 200601031370; sp insp required | ||
| Jun 17, 2009 | Completed final sign-off Jun 2009 | 2201 Baker St | Serrano Fire Protection Systems | as built to previous pa# 2008-1204-7794-using 2" fire service instead of 2" combo, addition of (2) heads in garage storage units.Details
as built to previous pa# 2008-1204-7794-using 2" fire service instead of 2" combo, addition of (2) heads in garage storage units. | |
| Mar 18, 2009 | Completed final sign-off Aug 2009 | 2201 Baker St | to rebuilt and enlarge extg dormer on extg roof and top floor area only.Details
to rebuilt and enlarge extg dormer on extg roof and top floor area only. | $5,500 | |
| Jan 14, 2009 | Never finaled issued Jan 2009, no final | 2201 Baker St | street space permit only. | ||
| Dec 4, 2008 | Completed final sign-off Aug 2009 | 2201 Baker St | Serrano Fire Protection Systems | full installation of nfpa 13 fire sprinkler system throughout the building total 111 sprinkler heads. ord. 1 for garage, light haz for residential- includes new underground & 2" inches combo meter.Details
full installation of nfpa 13 fire sprinkler system throughout the building total 111 sprinkler heads. ord. 1 for garage, light haz for residential- includes new underground & 2" inches combo meter. | $20,000 |
| Oct 14, 2008 | Never finaled issued Oct 2008, no final | 2201 Baker St | street space permit | ||
| Oct 8, 2008 | Expired or cancelled expired Aug 2009 | 2201 Baker St | comply (partially) with nov# 200802064121 to restore roof to (e), original condition as per request by dcp. lower approx 21" per city planning approval. additional permit will be filed to comply with n.o.vDetails
comply (partially) with nov# 200802064121 to restore roof to (e), original condition as per request by dcp. lower approx 21" per city planning approval. additional permit will be filed to comply with n.o.v | $10,000 | |
| Jun 27, 2008 | Never finaled issued Jun 2008, no final | 2201 Baker St | Occidental Express | replacing roof shingles including composition shingles.Details
replacing roof shingles including composition shingles. | $28,000 |
| Apr 14, 2008 | Expired or cancelled expired Mar 2026 | 2201 Baker St | to install new interior elevator at all floors.Details
to install new interior elevator at all floors. | $10,000 | |
| Mar 12, 2008 | Never finaled issued Mar 2008, no final | 2201 Baker St | street space | ||
| Mar 6, 2008 | Never finaled issued Mar 2008, no final | 2201 Baker St | replace cracked slab with new slab on grade & grade beamDetails
replace cracked slab with new slab on grade & grade beam | $8,000 | |
| Feb 6, 2008 | Expired or cancelled expired Aug 2009 | 2201 Baker St | Cullinane Plastering | int. alterations to (e)4 story bldg,(n) systems, minor ext. alterations, all int. walls removed. 1st flr.:2(n) windows added & 11 to be replaced; 2nd. flr.:7(n) windows & 8 to be replaced; 3rd flr.:6(n) windows & 9 to be replaced.Details
int. alterations to (e)4 story bldg,(n) systems, minor ext. alterations, all int. walls removed. 1st flr.:2(n) windows added & 11 to be replaced; 2nd. flr.:7(n) windows & 8 to be replaced; 3rd flr.:6(n) windows & 9 to be replaced. | $300,000 |
| Sep 5, 2006 | Expired or cancelled cancelled Oct 2007 | 2201 Baker St | enlarge a section of the building on the north side to create a new set of stairs to connect all floorsDetails
enlarge a section of the building on the north side to create a new set of stairs to connect all floors | $20,000 | |
| Jan 3, 2006 | Expired or cancelled cancelled Nov 2009 | 2201 Baker St | remove brick foundation & replace it with a concrete foundation + replace partition walls + replace center support beam /wall.Details
remove brick foundation & replace it with a concrete foundation + replace partition walls + replace center support beam /wall. | $100,000 | |
| Dec 20, 2005 | Expired or cancelled cancelled Nov 2009 | 2201 Baker St | phase i of remodeling of (e) building. remodeling of (e) bedrooms & bathrooms on 2nd floors. no exterior work. work on 1st floor to remove 1/2 bath, closet & a wall.Details
phase i of remodeling of (e) building. remodeling of (e) bedrooms & bathrooms on 2nd floors. no exterior work. work on 1st floor to remove 1/2 bath, closet & a wall. | $40,000 | |
| Dec 2, 2005 | Expired or cancelled cancelled Nov 2009 | 2201 Baker St | enlarge extg 2 car garage within the extg envelope of the bldg/ perform some preliminary demolition opening 3x3 holes at ceilings on each room or the bldg for future remodelDetails
enlarge extg 2 car garage within the extg envelope of the bldg/ perform some preliminary demolition opening 3x3 holes at ceilings on each room or the bldg for future remodel | $30,000 | |
| Sep 13, 2005 | Expired or cancelled cancelled Nov 2009 | 2201 Baker St | removal of (e)stair as shown on sheet a2.3Details
removal of (e)stair as shown on sheet a2.3 | $1,000 | |
| Apr 12, 2005 | Completed final sign-off Nov 2005 | 2201 Baker St | change of joccupancy class only no constructiion to takeplace on property all drawings are shownDetails
change of joccupancy class only no constructiion to takeplace on property all drawings are shown |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Serrano Fire Protection Systems (2), Cairn Construction, Cullinane Plastering, Occidental Express
- Architects
- Abraham Zavala (2), Mark English (2), Barbara Maria Roczniak
- Engineers
- Santos & Urrutia Assoc. (2), Abraham Zavala
Find contractors for work like this