Permit GraphShortlistSan Francisco building permits since 2000

Block 0843, lot 004

445 Fillmore St

City’s use
Commercial Misc
Built
1925
Stories
2
Units
1
Rooms
2 bathrooms
Building
13,298 sq ft
Lot
6,982 sq ft
Zoning
RM1
Construction type
C

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

23 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Sep 18, 2026In progress
filed Sep 2026, not yet issued
445 Fillmore Stt.i. of (e) offices. level 1 and 2.
Details
Permit
202609188335

t.i. of (e) offices. level 1 and 2.

Open the permit page

$3,022,000
Dec 12, 2019Completed
final sign-off Nov 2020
445 Fillmore StLegacy Mechanical & Energy Services, Inclike for like replacement of (4) rooftop ac units n/a maher
Details
Permit
201912129287
Permit issued
Dec 12, 2019
Final sign-off
Nov 17, 2020

like for like replacement of (4) rooftop ac units n/a maher

Open the permit page

$40,000
Dec 9, 2009Never finaled
issued Dec 2009, no final
445 Fillmore StEternal Construction Inc.to obtain final inspection for work approved under pa #200211131258
Details
Permit
200912092933
Permit issued
Dec 9, 2009

to obtain final inspection for work approved under pa #200211131258

Open the permit page

Dec 9, 2009Never finaled
issued Dec 2009, no final
445 Fillmore StEternal Construction Inc.to obtain final inspection for work approved under pa #200303250660
Details
Permit
200912092936
Permit issued
Dec 9, 2009

to obtain final inspection for work approved under pa #200303250660

Open the permit page

Dec 9, 2009Never finaled
issued Dec 2009, no final
445 Fillmore StEternal Construction Inc.to obtain final inspection for work approved under pa #200303250660
Details
Permit
200912092934
Permit issued
Dec 9, 2009

to obtain final inspection for work approved under pa #200303250660

Open the permit page

Dec 9, 2009Never finaled
issued Dec 2009, no final
445 Fillmore StEternal Construction Inc.to obtain final inspection for work approved under pa #200401164226.
Details
Permit
200912092935
Permit issued
Dec 9, 2009

to obtain final inspection for work approved under pa #200401164226.

Open the permit page

Nov 3, 2009Never finaled
issued Nov 2009, no final
445 Fillmore StEternal Construction Inc.revision to application 200211131258. revised parking layout. change order # 1.
Details
Permit
200911030475
Permit issued
Nov 10, 2009

revision to application 200211131258. revised parking layout. change order # 1.

Open the permit page

$500
Dec 10, 2008Expired or cancelled
expired Dec 2009
445 Fillmore Stcomplete work and obtain final inspection for work under permit #20021131258.
Details
Permit
200812108229
Permit issued
Dec 10, 2008

complete work and obtain final inspection for work under permit #20021131258.

Open the permit page

$50,000
Dec 3, 2004Completed
final sign-off Jan 2005
445 Fillmore StThe Lawson Roofing Co Inc.reroofing
Details
Permit
200412030663
Permit issued
Dec 3, 2004
Final sign-off
Jan 26, 2005

reroofing

Open the permit page

$89,500
May 25, 2004Never finaled
issued May 2004, no final
445 Fillmore Stexisting material below 4(e) windows is poorly patched replace area below 4(e) window with new reinf
Details
Permit
200405254755
Permit issued
May 25, 2004

existing material below 4(e) windows is poorly patched replace area below 4(e) window with new reinf

Open the permit page

$1,200
Jan 16, 2004Never finaled
issued Jan 2004, no final
445 Fillmore Stfirst floor concrete slab and drainage repair revised to approved 200211131258
Details
Permit
200401164226
Permit issued
Jan 16, 2004

first floor concrete slab and drainage repair revised to approved 200211131258

Open the permit page

$20,000
Mar 25, 2003Never finaled
issued Mar 2003, no final
445 Fillmore Stto erect a single-faced non electric wall sign
Details
Permit
200303250660
Permit issued
Mar 25, 2003

to erect a single-faced non electric wall sign

Open the permit page

Nov 13, 2002Never finaled
issued Dec 2002, no final
445 Fillmore Sttenants improvements by adding offices on 2nd & 1st floor space up-grading parking.
Details
Permit
200211131258
Permit issued
Dec 18, 2002

tenants improvements by adding offices on 2nd & 1st floor space up-grading parking.

Open the permit page

$150,000
Jan 16, 2001Completed
final sign-off Feb 2001
445 Fillmore Stminor revision to appl#200011145691 & 200007256092r1. lower entry & ramp, move door to front of bldg
Details
Permit
200101169870
Permit issued
Feb 13, 2001
Final sign-off
Feb 26, 2001

minor revision to appl#200011145691 & 200007256092r1. lower entry & ramp, move door to front of bldg

Open the permit page

Dec 8, 2000Completed
final sign-off Feb 2001
445 Fillmore Strevise 200007256092: clarifications to structural details per inspector's request
Details
Permit
200012087581
Permit issued
Dec 19, 2000
Final sign-off
Feb 26, 2001

revise 200007256092: clarifications to structural details per inspector's request

Open the permit page

$1,000
Nov 20, 2000Expired or cancelled
expired Mar 2001
445 Fillmore Stsidewalk
Details
Permit
M15037
Permit issued
Nov 20, 2000

sidewalk

Open the permit page

Nov 14, 2000Completed
final sign-off Feb 2001
445 Fillmore Stnew mechanical systems-main bldg improvements under appvd 200007256092-change of occupncy frm s3 tob
Details
Permit
200011145686
Permit issued
Dec 28, 2000
Final sign-off
Feb 26, 2001

new mechanical systems-main bldg improvements under appvd 200007256092-change of occupncy frm s3 tob

Open the permit page

$40,000
Nov 14, 2000Completed
final sign-off Feb 2001
445 Fillmore Stchange in occupancy from s-3 to b minor nonstructural partitions changes to pa#200007256092
Details
Permit
200011145691
Permit issued
Dec 6, 2000
Final sign-off
Feb 26, 2001

change in occupancy from s-3 to b minor nonstructural partitions changes to pa#200007256092

Open the permit page

$10,000
Aug 10, 2000Completed
final sign-off Feb 2001
445 Fillmore Stinterior demo -removal of int concrete auto ramp-minor partition removal, roof membrane removal-tar
Details
Permit
200008107553
Permit issued
Aug 10, 2000
Final sign-off
Feb 26, 2001

interior demo -removal of int concrete auto ramp-minor partition removal, roof membrane removal-tar

Open the permit page

$20,000
Jul 25, 2000Completed
final sign-off Feb 2001
445 Fillmore Stremove concrete auto ramps to 2nd fl.2 new stairs &elevator,2dr,accessible bathrms, upgrade seismic.
Details
Permit
200007256092
Permit issued
Sep 8, 2000
Final sign-off
Feb 26, 2001

remove concrete auto ramps to 2nd fl.2 new stairs &elevator,2dr,accessible bathrms, upgrade seismic.

Open the permit page

$200,000
Jun 26, 2000Completed
final sign-off Feb 2001
445 Fillmore Stexploratory demo. limited to 2-4" core of 2nd flo slab
Details
Permit
200006263645
Permit issued
Jun 26, 2000
Final sign-off
Feb 26, 2001

exploratory demo. limited to 2-4" core of 2nd flo slab

Open the permit page

$1,500
May 26, 2000Expired or cancelled
withdrawn Aug 2000
445 Fillmore Sttenant improvement.
Details
Permit
200005261171

tenant improvement.

Open the permit page

$150,000
May 26, 2000Expired or cancelled
withdrawn Aug 2000
445 Fillmore Ststructural, core & shell upgrade.
Details
Permit
200005261167

structural, core & shell upgrade.

Open the permit page

$250,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Eternal Construction Inc. (5), Legacy Mechanical & Energy Services, Inc, The Lawson Roofing Co Inc.
Architects
Steven Stenton, Will Revilock
Engineers
Kerry Macdonlad
Authorized agents
Will Revilock

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.