Block 0738, lot 018
830 Eddy St
- City’s use
- Multi-Family Residential
- Built
- 2021
- Stories
- 12
- Units
- 137
- Building
- 95,303 sq ft
- Lot
- 13,200 sq ft
- Zoning
- RC4
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
19 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 18, 2021 | Completed final sign-off Aug 2025 | 830 Eddy St | Ghilotti Bros Inc | administrative permit to record declarition of restriction under 201612285985. no work perform under this permit. declarition of restriction between 830 eddy and 203 willow/ 815-825 van ness propertiesDetails
administrative permit to record declarition of restriction under 201612285985. no work perform under this permit. declarition of restriction between 830 eddy and 203 willow/ 815-825 van ness properties | |
| Oct 7, 2021 | Completed final sign-off Aug 2025 | 830 Eddy St | Webcor Construction Lp | administrative correction to site permit #2016-1228-5985; to clarify location of 2 code required car share spaces per planning commission motion #19819 associated with cua# 2015-00946 cuaDetails
administrative correction to site permit #2016-1228-5985; to clarify location of 2 code required car share spaces per planning commission motion #19819 associated with cua# 2015-00946 cua | |
| Aug 6, 2021 | Completed final sign-off Sep 2021 | 830 Eddy St | Webcor Construction Lp | administrative permit to correct unit count on permit application of app# 201612285985 from 126 to 137 units per approved site permit drawings.Details
administrative permit to correct unit count on permit application of app# 201612285985 from 126 to 137 units per approved site permit drawings. | |
| Jul 20, 2021 | Completed final sign-off Aug 2025 | 830 Eddy St | Webcor Construction Lp | revision to 201612285985 r1 (fire alarm) and 56 w/ reused sequene of operation matrixDetails
revision to 201612285985 r1 (fire alarm) and 56 w/ reused sequene of operation matrix | |
| May 26, 2021 | Completed final sign-off Oct 2021 | 830 Eddy St | Webcor Construction Lp | level 1 and 2 unit guardrails and roof level glass guardrails at roof parapet. shop drawings per approval under 201612285985Details
level 1 and 2 unit guardrails and roof level glass guardrails at roof parapet. shop drawings per approval under 201612285985 | |
| Apr 15, 2021 | Completed final sign-off Sep 2023 | 830 Eddy St | Webcor Construction Lp | chaanges to fire pump switchboard amerage from 2000a to 1200a to match the incoming 1200a 480/277v ucd service.Details
chaanges to fire pump switchboard amerage from 2000a to 1200a to match the incoming 1200a 480/277v ucd service. | |
| Mar 23, 2021 | Completed final sign-off Jul 2021 | 830 Eddy St | Webcor Construction Lp | revision to pa# 201612285985 addendum 3. changes to an office and a bathroom at level 1 only.Details
revision to pa# 201612285985 addendum 3. changes to an office and a bathroom at level 1 only. | |
| Mar 11, 2021 | Completed final sign-off Jul 2021 | 830 Eddy St | Webcor Construction Lp | installatin of exterior building maintenance system, ref pa# 2016-1228-5985Details
installatin of exterior building maintenance system, ref pa# 2016-1228-5985 | $10,000 |
| Feb 25, 2021 | Completed final sign-off Aug 2025 | 830 Eddy St | Signcraft Inc | install fory four (44) 18" x 18" emergency evac plansDetails
install fory four (44) 18" x 18" emergency evac plans | $1,500 |
| Jul 22, 2020 | Completed final sign-off Nov 2023 | 830 Eddy St | Webcor Construction Lp | installation of a new 8" fire water service totaling approx 23'-3", backflow preventer, and two fire department connections servicing a new 13-story structure with 3-levels below grade parking, connecting to an existing 8" main on eddy street.Details
installation of a new 8" fire water service totaling approx 23'-3", backflow preventer, and two fire department connections servicing a new 13-story structure with 3-levels below grade parking, connecting to an existing 8" main on eddy street. | $10,000 |
| Jun 11, 2020 | Never finaled issued Jun 2020, no final | 830 Eddy St | street spaceDetails
street space | ||
| Mar 12, 2020 | Completed final sign-off Sep 2021 | 830 Eddy St | Allied Fire Protection | relocate portion of underground 6" tie in to existing utilityDetails
relocate portion of underground 6" tie in to existing utility | $2,500 |
| Jan 8, 2020 | Completed final sign-off Feb 2020 | 830 Eddy St | Granite Excavation & Demolition Inc | courtyard: temporary relocation o fexisting 6" fire line during construction to allow soldier beam install. fittings include 6" mega long connectors bend fitting at 90, 45, and/or 22 degrees. reference pa #2019-0419-8522Details
courtyard: temporary relocation o fexisting 6" fire line during construction to allow soldier beam install. fittings include 6" mega long connectors bend fitting at 90, 45, and/or 22 degrees. reference pa #2019-0419-8522 | $10,000 |
| Nov 14, 2019 | Completed final sign-off Aug 2021 | 830 Eddy St | Webcor Construction Lp | tower crane permit approvalDetails
tower crane permit approval | $223,204 |
| Apr 19, 2019 | Completed final sign-off Oct 2021 | 830 Eddy St | Webcor Construction Lp | landscape improvements associated with 203 willow. portions of landscape+fencing that spans along property line. bpa 2019-0419-8473.Details
landscape improvements associated with 203 willow. portions of landscape+fencing that spans along property line. bpa 2019-0419-8473. | $5,000 |
| Apr 15, 2019 | Completed final sign-off Jul 2021 | 830 Eddy St | Webcor Construction Lp, Granite Excavation & Demolition Inc | install temporary shoring and underpinning along property lines to allow excavation for new development @ 830 eddy st.**maher n/a**Details
install temporary shoring and underpinning along property lines to allow excavation for new development @ 830 eddy st.**maher n/a** | $500,000 |
| Oct 6, 2017 | Completed final sign-off Nov 2021 | 830 Eddy St | to demolish 2 story parking garage building.Details
to demolish 2 story parking garage building. | $100,000 | |
| Dec 28, 2016 | Completed final sign-off Jun 2024 | 830 Eddy St | Webcor Construction Lp | to erect 13 stories, 3 basements, type i-a, 126 residential units with parking building.Details
to erect 13 stories, 3 basements, type i-a, 126 residential units with parking building. | $38,700,000 |
| Oct 12, 2001 | Expired or cancelled cancelled May 2002 | 830 Eddy St | re-stripparking w/ one hcp space & signage, change out 16 (e) lt fixt new fix relocate hc park spaceDetails
re-stripparking w/ one hcp space & signage, change out 16 (e) lt fixt new fix relocate hc park space | $7,200 |
Find contractors for work like this