Block 0685, lot 012
1746 Post St
- City’s use
- Commercial Retail
- Built
- 2009
- Stories
- 3
- Units
- 1
- Building
- 20,968 sq ft
- Lot
- 5,566 sq ft
- Zoning
- NC2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
35 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 13, 2010 | Never finaled issued Jan 2010, no final | 1746 Post St | street space & mtaDetails
street space & mta | ||
| Sep 10, 2009 | Completed final sign-off Feb 2010 | 1746 Post St | Pribuss Engineering Inc | fire sprinkler t.i (common area)-add 2 sprinklers, relocate 1Details
fire sprinkler t.i (common area)-add 2 sprinklers, relocate 1 | $700 |
| Sep 10, 2009 | Completed final sign-off Feb 2010 | 1746 Post St | Pribuss Engineering Inc | 1st floor-fire sprinkler t.i (common area)-add 1 sprinklerDetails
1st floor-fire sprinkler t.i (common area)-add 1 sprinkler | $250 |
| Sep 10, 2009 | Completed final sign-off Feb 2010 | 1746 Post St | Pribuss Engineering Inc | 2nd floor-fire sprinkler t.i-add 1 sprinklerDetails
2nd floor-fire sprinkler t.i-add 1 sprinkler | $250 |
| Sep 10, 2009 | Completed final sign-off Feb 2010 | 1746 Post St | Pribuss Engineering Inc | 2nd floor-fire sprinkler t.i-add 2 sprinklers, relocate 1Details
2nd floor-fire sprinkler t.i-add 2 sprinklers, relocate 1 | $1,200 |
| Aug 10, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | revision to appl #200707166813-s3/r1 - clarification: 2 hr glass floor infill panel @ 2nd floor, not 1 hr due to 2 hr lobby.Details
revision to appl #200707166813-s3/r1 - clarification: 2 hr glass floor infill panel @ 2nd floor, not 1 hr due to 2 hr lobby. | |
| Aug 5, 2009 | Never finaled issued Aug 2009, no final | 1746 Post St | street space permitDetails
street space permit | ||
| Jun 2, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | to obtain final inspection for work approved under app #200711168343. all work is completeDetails
to obtain final inspection for work approved under app #200711168343. all work is complete | |
| Jun 2, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | to obtain final inspection for work approved under app #200802134703. all work is completeDetails
to obtain final inspection for work approved under app #200802134703. all work is complete | |
| May 27, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | remove and add fire damper in the basement. revision to pa# 200707166813 ( new construction)Details
remove and add fire damper in the basement. revision to pa# 200707166813 ( new construction) | $400 |
| Apr 29, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | tenant improvement-build-out on 2nd floor approx. 2,046 s.f. w/ future retail spaces (2x) & elevator lobby; includes interior walls, finishes, mech. & elec.Details
tenant improvement-build-out on 2nd floor approx. 2,046 s.f. w/ future retail spaces (2x) & elevator lobby; includes interior walls, finishes, mech. & elec. | $40,000 |
| Apr 10, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | 3rd floor office: tenant improvement build out on 3rd floor. (apporx 4,044 sf) with private office, office showroom, open workspace and storage area. scope of work includes interior walls, millwork, finishes, mechanical, electrical and plumbing.Details
3rd floor office: tenant improvement build out on 3rd floor. (apporx 4,044 sf) with private office, office showroom, open workspace and storage area. scope of work includes interior walls, millwork, finishes, mechanical, electrical and plumbing. | $105,000 |
| Mar 20, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | tenant improvement retail space 1985 sf-open bookstore/retail area including storage & cashier stand. interior walls, millwork, finishes & mech & elec.Details
tenant improvement retail space 1985 sf-open bookstore/retail area including storage & cashier stand. interior walls, millwork, finishes & mech & elec. | $75,000 |
| Mar 10, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | 2nd floor; baby-tenant improvement retail space 1030 sf: 2 fitting rooms, storage area, lighting, return & supply registers.Details
2nd floor; baby-tenant improvement retail space 1030 sf: 2 fitting rooms, storage area, lighting, return & supply registers. | $70,000 |
| Mar 10, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | 2nd floor; black peace now-tenant improvement retail space 1000 sf: 2 fitting rooms, storage area, lighting, return & supply registers.Details
2nd floor; black peace now-tenant improvement retail space 1000 sf: 2 fitting rooms, storage area, lighting, return & supply registers. | $70,000 |
| Feb 10, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Fire & Security & Alarm Co/ F.S.A.C. | install new addressable fire alarm system, ref pa #200707166813.Details
install new addressable fire alarm system, ref pa #200707166813. | $40,000 |
| Feb 3, 2009 | Never finaled issued Feb 2009, no final | 1746 Post St | street space & mtaDetails
street space & mta | ||
| Jan 14, 2009 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | revision to appl #200707166813s3-r1 - revise cafe layout - adding some kitchen equipments & a dry storage w/mop sink at retail.Details
revision to appl #200707166813s3-r1 - revise cafe layout - adding some kitchen equipments & a dry storage w/mop sink at retail. | $5,000 |
| Dec 5, 2008 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | change stair #2 & 3 walls rating from 2 to 1 hour except stair #2 walls @ ground floor to remain 2 hrs. change 1st fl. walls from 2 hrs to 1 hr. from gl c-d change 2nd & 3rd flrs walls from 2 hrs to 1 hr from gl a-d. revision to application 200707166813s-3r-1.Details
change stair #2 & 3 walls rating from 2 to 1 hour except stair #2 walls @ ground floor to remain 2 hrs. change 1st fl. walls from 2 hrs to 1 hr. from gl c-d change 2nd & 3rd flrs walls from 2 hrs to 1 hr from gl a-d. revision to application 200707166813s-3r-1. | |
| Nov 26, 2008 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | revision to structural addendum: wood trusses and steel trusses (deferred submittal) under permit#:2007-0716-6813Details
revision to structural addendum: wood trusses and steel trusses (deferred submittal) under permit#:2007-0716-6813 | |
| Nov 18, 2008 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | the arrangement of the hvac duct has been modified per app #200707166813 s4Details
the arrangement of the hvac duct has been modified per app #200707166813 s4 | $100 |
| Sep 17, 2008 | Completed final sign-off Oct 2009 | 1746 Post St | Pribuss Engineering Inc | add 224 sprinkler heads - entire building. new system including new meter and connection, new standpipe system.Details
add 224 sprinkler heads - entire building. new system including new meter and connection, new standpipe system. | $56,000 |
| Aug 5, 2008 | Never finaled issued Aug 2008, no final | 1746 Post St | street space only.Details
street space only. | ||
| Feb 21, 2008 | Completed final sign-off Oct 2009 | 1746 Post St | Oliver & Company Inc. | erect tower crane per ab-023.Details
erect tower crane per ab-023. | |
| Feb 13, 2008 | Expired or cancelled expired Jan 2010 | 1746 Post St | Oliver & Company Inc. | build footing to accommodate tower crane, on vacant lot. per application #200707166813.Details
build footing to accommodate tower crane, on vacant lot. per application #200707166813. | $9,500 |
| Nov 16, 2007 | Never finaled issued Dec 2007, no final | 1746 Post St | revision to approv pa #200708291263: change of depth of excavation design 3' + or -.Details
revision to approv pa #200708291263: change of depth of excavation design 3' + or -. | ||
| Nov 16, 2007 | Completed final sign-off May 2009 | 1746 Post St | revised the demolition sequence to demolition permit #20707166811.Details
revised the demolition sequence to demolition permit #20707166811. | ||
| Aug 29, 2007 | Expired or cancelled cancelled Oct 2009 | 1746 Post St | provide temporary shoring, excavation and soldier beams per plan. erect building under appl#200707166813.Details
provide temporary shoring, excavation and soldier beams per plan. erect building under appl#200707166813. | $160,000 | |
| Jul 20, 2007 | Completed final sign-off Sep 2007 | 1746 Post St | Asbetos Management Group | removal of drywall and ceiling, flooring. build full containment inside building. install negative air pressure system, use wet methods to remove asbestos, lead containing materialDetails
removal of drywall and ceiling, flooring. build full containment inside building. install negative air pressure system, use wet methods to remove asbestos, lead containing material | $10,000 |
| Jul 16, 2007 | Completed final sign-off Oct 2009 | 1746 Post St | erect 3 stories, 1 basement, assembly/office/retail building.Details
erect 3 stories, 1 basement, assembly/office/retail building. | $2,000,000 | |
| Jul 16, 2007 | Completed final sign-off May 2009 | 1746 Post St | demolish 2 stories, print shop. complaint #200714936 (bid-insp).Details
demolish 2 stories, print shop. complaint #200714936 (bid-insp). | ||
| Jan 21, 2005 | Completed final sign-off Dec 2005 | 1746 Post St | renewal of shoring & underpinning 200302207862-renewal of cornice 200310177844 for final inspectionDetails
renewal of shoring & underpinning 200302207862-renewal of cornice 200310177844 for final inspection | ||
| Oct 17, 2003 | Expired or cancelled expired Dec 2005 | 1746 Post St | remove cornice encroachment 14" wide & 42" long onto adjacent lot 685/51Details
remove cornice encroachment 14" wide & 42" long onto adjacent lot 685/51 | $100 | |
| Aug 26, 2003 | Completed final sign-off Sep 2003 | 1746 Post St | J. Handa Construction | repair northwest corner of property where new construction of adjacent property will cover. proposedDetails
repair northwest corner of property where new construction of adjacent property will cover. proposed | $2,000 |
| Feb 20, 2003 | Expired or cancelled expired Mar 2006 | 1746 Post St | shoring and underpinning as required for adjacent new const. @ 1600 webster st bpn #200203262363sDetails
shoring and underpinning as required for adjacent new const. @ 1600 webster st bpn #200203262363s | $60,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Oliver & Company Inc. (15), Pribuss Engineering Inc (5), Asbetos Management Group, Fire & Security & Alarm Co/ F.S.A.C., J. Handa Construction
- Architects
- Denis Henmi (5), Carl Chan
- Engineers
- Carl Chan, Raymond Brooks
- Authorized agent-otherss
- Sure Engineering
Find contractors for work like this