Block 0533, lot 001
2961 Webster St
- City’s use
- Commercial Misc
- Built
- 1905
- Stories
- 4
- Rooms
- 3 bathrooms
- Lot
- 2,495 sq ft
- Zoning
- RH2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
22 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 16, 2017 | Never finaled issued Mar 2017, no final | 2961 Webster St | Christopher's Construction Inc | street space permitDetails
street space permit | |
| Feb 13, 2017 | Never finaled issued Feb 2017, no final | 2961 Webster St | Christopher's Construction Inc | to obtain final inspection for work approved under pa# 201411192022. all work is complete.Details
to obtain final inspection for work approved under pa# 201411192022. all work is complete. | |
| Jan 19, 2017 | Never finaled issued Jan 2017, no final | 2961 Webster St | street spaceDetails
street space | ||
| Nov 17, 2016 | Never finaled issued Nov 2016, no final | 2961 Webster St | street space permitDetails
street space permit | ||
| Aug 11, 2016 | Never finaled issued Aug 2016, no final | 2961 Webster St | street spaceDetails
street space | ||
| Jun 14, 2016 | Never finaled issued Jun 2016, no final | 2961 Webster St | street space permitDetails
street space permit | ||
| Mar 4, 2016 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | revision to pa 2014-1014-8843, replace rear door on north elevation. change interior basement doors as noted on plan. maher naDetails
revision to pa 2014-1014-8843, replace rear door on north elevation. change interior basement doors as noted on plan. maher na | $500 |
| Jan 21, 2016 | Never finaled issued Jan 2016, no final | 2961 Webster St | street space permit - renewal of permit # m600227Details
street space permit - renewal of permit # m600227 | ||
| Dec 22, 2015 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | revision to app#201410148843 structural and architectural changes per as built conditions. n/a for maherDetails
revision to app#201410148843 structural and architectural changes per as built conditions. n/a for maher | $1,000 |
| Dec 11, 2015 | Completed final sign-off Mar 2017 | 2961 Webster St | Crime Watch Security Sys Llc | sprinkler water flow and supervisory system. install new control unit, smoke det. above and pull station near panel. install monitor modules to tie in water flow, tamper switches and ansul system to new panel for monitoring. ti #201410148843 & 201506199381Details
sprinkler water flow and supervisory system. install new control unit, smoke det. above and pull station near panel. install monitor modules to tie in water flow, tamper switches and ansul system to new panel for monitoring. ti #201410148843 & 201506199381 | $3,800 |
| Sep 18, 2015 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | replacement in kind of (e) double hung windows with wood clad double hung windows (south east & north facades), replace lightwell windows. n/a ordinance #155-13Details
replacement in kind of (e) double hung windows with wood clad double hung windows (south east & north facades), replace lightwell windows. n/a ordinance #155-13 | $15,000 |
| Jul 6, 2015 | Never finaled issued Jul 2015, no final | 2961 Webster St | street spaceDetails
street space | ||
| Jun 19, 2015 | Completed final sign-off Mar 2017 | 2961 Webster St | Fire Guard Protection Inc. | install fire sprinkler system throughout per nfp-13. bldg permit #201410148843 r-1 and 201506058315. n/a for the maher.Details
install fire sprinkler system throughout per nfp-13. bldg permit #201410148843 r-1 and 201506058315. n/a for the maher. | $25,000 |
| Jun 5, 2015 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | revision appl. 2014.1014.8843. change occupancy of basement storage to a-3 assembly meeting room and office per plan. entire building to be fully sprinklered under separate permit. maher n/a.Details
revision appl. 2014.1014.8843. change occupancy of basement storage to a-3 assembly meeting room and office per plan. entire building to be fully sprinklered under separate permit. maher n/a. | $2,500 |
| May 22, 2015 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | remove and replace metal roof cladding and details as shown. new cladding and details to copper and to match extg forms.Details
remove and replace metal roof cladding and details as shown. new cladding and details to copper and to match extg forms. | $40,000 |
| Feb 2, 2015 | Never finaled issued Feb 2015, no final | 2961 Webster St | street spaceDetails
street space | ||
| Dec 2, 2014 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | rev. to pa# 201407151361 structural details revised. n/a ordinance #155-13Details
rev. to pa# 201407151361 structural details revised. n/a ordinance #155-13 | $30,000 |
| Nov 19, 2014 | Never finaled issued Dec 2014, no final | 2961 Webster St | Christopher's Construction Inc | shoring of 2nd fl of existing building by means of wood cribbing and steel shoring , beams additional work to 201407151361. n/a for maherDetails
shoring of 2nd fl of existing building by means of wood cribbing and steel shoring , beams additional work to 201407151361. n/a for maher | $10,000 |
| Oct 14, 2014 | Completed final sign-off Apr 2017 | 2961 Webster St | Christopher's Construction Inc | lateral strengthening, lower (e) slab @ basement approx 4 feet deep w/ new foundation. new bathrooms & laundry at basement level. remodel kitchen & bathrooms at second level, relocate 1 and install new bathroom at 3rd level.Details
lateral strengthening, lower (e) slab @ basement approx 4 feet deep w/ new foundation. new bathrooms & laundry at basement level. remodel kitchen & bathrooms at second level, relocate 1 and install new bathroom at 3rd level. | $140,000 |
| Jul 15, 2014 | Completed final sign-off Apr 2017 | 2961 Webster St | S F Garage Company Inc., Christopher's Construction Inc | upgrade of basement level (strengthening) and foundation replacement. compliance with maher ordinance no 155-13 not required.Details
upgrade of basement level (strengthening) and foundation replacement. compliance with maher ordinance no 155-13 not required. | $49,000 |
| Jul 11, 2014 | Never finaled issued Jul 2014, no final | 2961 Webster St | street space permitDetails
street space permit | ||
| Jul 1, 2005 | Never finaled issued Jul 2005, no final | 2961 Webster St | street spaceDetails
street space |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Christopher's Construction Inc (11), Crime Watch Security Sys Llc, Fire Guard Protection Inc., S F Garage Company Inc.
- Architects
- Shawn Gorman (4), Shawn Gorman (2)
- Engineers
- Rodrigo Santos (4), Santos & Urruta
Find contractors for work like this