FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jun 20, 2018Completed
final sign-off Mar 2023
538 Eddy Stremove (e) fencing-fence foundation and pylor. install (n) security & gates & fencing. work is on eddy st
Details
Permit
201806202489
Status
complete
Filed
Jun 20, 2018
Permit issued
Jul 24, 2018
Final sign-off
Mar 1, 2023
Declared cost
$50,000
Address
538 Eddy St

remove (e) fencing-fence foundation and pylor. install (n) security & gates & fencing. work is on eddy st

Open the permit page

$50,000
Jun 4, 2018Never finaled
issued Jun 2018, no final
538 Eddy Ststreet space
Details
Permit
M934027
Status
issued
Filed
Jun 4, 2018
Permit issued
Jun 4, 2018
Address
538 Eddy St

street space

Open the permit page

May 9, 2018Completed
final sign-off May 2018
538 Eddy StPlant Construction Co, Lpexterior gfrc rainscreen cladding. ref pa 2015-1123-3360
Details
Permit
201805098599
Status
complete
Filed
May 9, 2018
Permit issued
May 14, 2018
Final sign-off
May 24, 2018
Declared cost
$375,000
Address
538 Eddy St

exterior gfrc rainscreen cladding. ref pa 2015-1123-3360

Open the permit page

$375,000
Mar 7, 2018Never finaled
issued Mar 2018, no final
538 Eddy Ststreet space, mta lf
Details
Permit
M897087
Status
issued
Filed
Mar 7, 2018
Permit issued
Mar 7, 2018
Address
538 Eddy St

street space, mta lf

Open the permit page

Feb 12, 2018Completed
final sign-off Dec 2022
538 Eddy Strevision to pa 2015-1123-3360 - civil drawings wtih underground utility revisions, including addition of sand interceptor for stormwater management planters
Details
Permit
201802120988
Status
complete
Filed
Feb 12, 2018
Permit issued
Feb 26, 2018
Final sign-off
Dec 22, 2022
Declared cost
$10,000
Address
538 Eddy St

revision to pa 2015-1123-3360 - civil drawings wtih underground utility revisions, including addition of sand interceptor for stormwater management planters

Open the permit page

$10,000
Sep 27, 2017Never finaled
issued Sep 2017, no final
538 Eddy Ststreet space
Details
Permit
M836427
Status
issued
Filed
Sep 27, 2017
Permit issued
Sep 27, 2017
Address
538 Eddy St

street space

Open the permit page

Sep 13, 2017Never finaled
issued Sep 2017, no final
538 Eddy Ststreet space
Details
Permit
M831608
Status
issued
Filed
Sep 13, 2017
Permit issued
Sep 15, 2017
Address
538 Eddy St

street space

Open the permit page

Jul 28, 2017Completed
final sign-off Dec 2022
538 Eddy StPlant Construction Co, Lpinstallation of screen mesh support framing. ref. pa #201511233360
Details
Permit
201707283252
Status
complete
Filed
Jul 28, 2017
Permit issued
May 14, 2018
Final sign-off
Dec 22, 2022
Declared cost
$100,000
Address
538 Eddy St

installation of screen mesh support framing. ref. pa #201511233360

Open the permit page

$100,000
Apr 5, 2017Completed
final sign-off Dec 2022
538 Eddy StPlant Construction Co, Lppg&e larkin stairs #1 & #2. new construction of engineered stairs to new bld. ref 201511233360. maher na
Details
Permit
201704053234
Status
complete
Filed
Apr 5, 2017
Permit issued
May 26, 2017
Final sign-off
Dec 22, 2022
Declared cost
$6,854,800
Address
538 Eddy St

pg&e larkin stairs #1 & #2. new construction of engineered stairs to new bld. ref 201511233360. maher na

Open the permit page

$6,854,800
Mar 21, 2017Never finaled
issued Mar 2017, no final
538 Eddy Ststreet space
Details
Permit
M769787
Status
issued
Filed
Mar 21, 2017
Permit issued
Mar 21, 2017
Address
538 Eddy St

street space

Open the permit page

Feb 27, 2017Never finaled
issued Mar 2017, no final
538 Eddy Ststreet space/mta
Details
Permit
M764228
Status
issued
Filed
Feb 27, 2017
Permit issued
Mar 8, 2017
Address
538 Eddy St

street space/mta

Open the permit page

Oct 21, 2016Completed
final sign-off Dec 2022
538 Eddy StPlant Construction Co, Lpbrb system for steel structural under permit 201511233360. ** maher: n/a **
Details
Permit
201610210857
Status
complete
Filed
Oct 21, 2016
Permit issued
Dec 23, 2016
Final sign-off
Dec 22, 2022
Declared cost
$32,750
Address
538 Eddy St

brb system for steel structural under permit 201511233360. ** maher: n/a **

Open the permit page

$32,750
Sep 21, 2016Completed
final sign-off Dec 2022
538 Eddy StPlant Construction Co, Lprevision to app#201511233360; revisions consist only of modifications to one brace frame element(structure only). no additional scope added or removed.
Details
Permit
201609218396
Status
complete
Filed
Sep 21, 2016
Permit issued
Sep 27, 2016
Final sign-off
Dec 22, 2022
Declared cost
$18,000
Address
538 Eddy St

revision to app#201511233360; revisions consist only of modifications to one brace frame element(structure only). no additional scope added or removed.

Open the permit page

$18,000
Aug 2, 2016Completed
final sign-off Dec 2022
538 Eddy StPlant Construction Co, Lpshoring system for basement excavation under 201511233360 maher 0req
Details
Permit
201608023917
Status
complete
Filed
Aug 2, 2016
Permit issued
Nov 23, 2016
Final sign-off
Dec 22, 2022
Declared cost
$350,000
Address
538 Eddy St

shoring system for basement excavation under 201511233360 maher 0req

Open the permit page

$350,000
Nov 23, 2015Completed
final sign-off Dec 2022
538 Eddy StPlant Construction Co, Lperect 2-story, type 2-a, 1 basement, electrical switchgear building for pg&e.
Details
Permit
201511233360
Status
complete
Filed
Nov 23, 2015
Permit issued
Aug 5, 2016
Final sign-off
Dec 22, 2022
Declared cost
$6,854,800
Address
538 Eddy St

erect 2-story, type 2-a, 1 basement, electrical switchgear building for pg&e.

Open the permit page

$6,854,800

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Plant Construction Co, Lp (7)
Architects
Douglas Tom
Engineers
Devon Lumbard, Douglas Tom, Kai Shing Chu

Find contractors for work like this