Block 0164, lot 006
410 Pacific Av
The city’s assessor roll has no record for this parcel.
Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
9 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 2, 2020 | Never finaled issued Dec 2020, no final | 410 Pacific Av | Flow Masters Plumbing Inc | previous contractor abandoned permit # 2015-1009-9301. as-built drawings. no actual work done to system. underground and backflow already in place. provided hydraulic calculations.Details
previous contractor abandoned permit # 2015-1009-9301. as-built drawings. no actual work done to system. underground and backflow already in place. provided hydraulic calculations. | $2,000 |
| Nov 27, 2019 | Completed final sign-off Mar 2021 | 410 Pacific Av | Crime Watch Security Sys Llc | installation of new sprinkler monitoring system. reference pa#2015-0929-8338 & #2015-1009-9301Details
installation of new sprinkler monitoring system. reference pa#2015-0929-8338 & #2015-1009-9301 | $3,500 |
| Oct 29, 2019 | Completed final sign-off Oct 2021 | 410 Pacific Av | certificate of appropriateness for exterior painting only. no other scope of work.Details
certificate of appropriateness for exterior painting only. no other scope of work. | ||
| Sep 24, 2019 | Never finaled issued Sep 2019, no final | 410 Pacific Av | Canyon Construction | to obtain final inspection for work approved under pa# 201510099301. all work is complete.Details
to obtain final inspection for work approved under pa# 201510099301. all work is complete. | |
| Jan 29, 2016 | Never finaled issued Jan 2016, no final | 410 Pacific Av | Art Of Construction Inc | revision to pa 2015 0929 8338 - replace (e) ductwork w/newDetails
revision to pa 2015 0929 8338 - replace (e) ductwork w/new | |
| Jan 25, 2016 | Completed final sign-off May 2016 | 410 Pacific Av | Art Of Construction Inc | plan review for electrical work, all other work included in t.i. pa#201509298338Details
plan review for electrical work, all other work included in t.i. pa#201509298338 | |
| Oct 9, 2015 | Never finaled issued Oct 2015, no final | 410 Pacific Av | Alliance Fire Inc | installation of new fire sprinkler system throughout building per nfpa-13. project includes 4-inch underground. monitoring under separate permit. t.i. app#2015-0929-8338Details
installation of new fire sprinkler system throughout building per nfpa-13. project includes 4-inch underground. monitoring under separate permit. t.i. app#2015-0929-8338 | $14,000 |
| Sep 29, 2015 | Completed final sign-off May 2016 | 410 Pacific Av | Art Of Construction Inc | demo of (e) interior offices, build 2 new ada bathrooms, install new handrails on (e) stairs, paint interior. install new flooring throughout re duct (e) hvac system. add 4 skylightsDetails
demo of (e) interior offices, build 2 new ada bathrooms, install new handrails on (e) stairs, paint interior. install new flooring throughout re duct (e) hvac system. add 4 skylights | $250,000 |
| May 6, 2015 | Never finaled issued May 2015, no final | 410 Pacific Av | Oliver & Company Inc. | select demolition of non-structural interior partitions, ceilings & finishes. the proposed design will not exceed substantial changes per sfbc 3404.7.1 non-structural alterations. t.i. under separate permit- provide calculation for complaince of percentage of alteration as per pre-appl minutesDetails
select demolition of non-structural interior partitions, ceilings & finishes. the proposed design will not exceed substantial changes per sfbc 3404.7.1 non-structural alterations. t.i. under separate permit- provide calculation for complaince of percentage of alteration as per pre-appl minutes | $25,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.