Block 0063, lot 005
1929 Stockton St
- City’s use
- Multi-Family Residential
- Built
- 1907
- Stories
- 3
- Units
- 7
- Rooms
- 12 bedrooms, 7 bathrooms
- Building
- 6,800 sq ft
- Lot
- 2,378 sq ft
- Zoning
- RM1
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
30 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 18, 2020 | Never finaled issued Oct 2020, no final | 1929 Stockton St | Crime Watch Security Sys Llc | installation of a new fire alarm system new silent knight fire alarm control unit, wireless fire alarm radio communicator , addressable manuel pull staion, addressable smoke detector, horn strobe and monitor.Details
installation of a new fire alarm system new silent knight fire alarm control unit, wireless fire alarm radio communicator , addressable manuel pull staion, addressable smoke detector, horn strobe and monitor. | $34,011 |
| Mar 10, 2020 | Completed final sign-off Apr 2021 | 9 Fielding St | kitchen and bath remodel in kind. remove/repair lathe & plaster as necessary. repair dry rot as necessary. no additional square footageDetails
kitchen and bath remodel in kind. remove/repair lathe & plaster as necessary. repair dry rot as necessary. no additional square footage | $20,000 | |
| Mar 4, 2020 | Completed final sign-off Apr 2021 | 1929 Stockton St | revision to pa 2019-0628-4735 provides additional details for roof deck & stair construction. no modifications to previously approved permit drawingsDetails
revision to pa 2019-0628-4735 provides additional details for roof deck & stair construction. no modifications to previously approved permit drawings | ||
| Mar 3, 2020 | Completed final sign-off Apr 2021 | 1929 Stockton St | 2 new windows at north elevation 3rd floor on secondary elevation; wood dh with integral ogee lugsDetails
2 new windows at north elevation 3rd floor on secondary elevation; wood dh with integral ogee lugs | $3,500 | |
| Feb 25, 2020 | Expired or cancelled cancelled Jan 2026 | 1929 Stockton St | revision pa# 201906284735: structral roof deckDetails
revision pa# 201906284735: structral roof deck | ||
| Dec 4, 2019 | Completed final sign-off Dec 2025 | 5 Fielding St | Crime Watch Security Sys Llc | replacement 2021 mandate installation a fully sprinklered building. replace of existing facu. install of new aes 7707, smoke detectors, pull station, low frequency, horn strobes, monitor modulesDetails
replacement 2021 mandate installation a fully sprinklered building. replace of existing facu. install of new aes 7707, smoke detectors, pull station, low frequency, horn strobes, monitor modules | $5,000 |
| Oct 30, 2019 | Completed final sign-off Nov 2019 | 1929 Stockton St | to obtain final inspection for work approved under pa# 201605197888. all work is complete.Details
to obtain final inspection for work approved under pa# 201605197888. all work is complete. | ||
| Oct 30, 2019 | Never finaled issued Oct 2019, no final | 5 Fielding St | 201910305965to obtain final inspection for work approved under pa# 201612013967. all work is complete.Details
201910305965to obtain final inspection for work approved under pa# 201612013967. all work is complete. | ||
| Oct 28, 2019 | Never finaled issued Oct 2019, no final | 1929 Stockton St | street spaceDetails
street space | ||
| Oct 28, 2019 | Completed final sign-off Apr 2021 | 7 Fielding St | remodel kitchen and bathroom. repair replace plaster as necessary. all (e) layout to remain. no change of floor plan. electrical and plumbing works excluded from this permitDetails
remodel kitchen and bathroom. repair replace plaster as necessary. all (e) layout to remain. no change of floor plan. electrical and plumbing works excluded from this permit | $20,000 | |
| Jun 28, 2019 | Completed final sign-off Apr 2021 | 1929 Stockton St | new roof top deck, new stair from one unit to roof deck with roof with roof access.1 hour parapet wall at p.l. for fire department roof top access.Details
new roof top deck, new stair from one unit to roof deck with roof with roof access.1 hour parapet wall at p.l. for fire department roof top access. | $30,000 | |
| Jul 2, 2018 | Expired or cancelled cancelled Aug 2023 | 5 Fielding St | Crime Watch Security Sys Llc | ref pa# 201612013967 & 201802060524; installation of a new sprinkler monitoring system, includes facu, wireless fa radio, (1) heat detector, (1) manual pull statin and (3) monitor modulesDetails
ref pa# 201612013967 & 201802060524; installation of a new sprinkler monitoring system, includes facu, wireless fa radio, (1) heat detector, (1) manual pull statin and (3) monitor modules | $3,500 |
| Feb 6, 2018 | Completed final sign-off Mar 2020 | 5 Fielding St | Project Contractor Inc | modify of fire sprinkler at ground floor only accommodate new partition per nfpa 13 ref total 9 sprinklers pa 2016-1201-3967.Details
modify of fire sprinkler at ground floor only accommodate new partition per nfpa 13 ref total 9 sprinklers pa 2016-1201-3967. | $5,400 |
| Dec 4, 2017 | Never finaled issued Dec 2017, no final | 1929 Stockton St | street spaceDetails
street space | ||
| Nov 17, 2017 | Never finaled issued Nov 2017, no final | 1929 Stockton St | street spaceDetails
street space | ||
| Sep 11, 2017 | Completed final sign-off May 2018 | 1929 Stockton St | repair siding and waterproof windows on n/s of building. repair dry rot siding on penthouse, replace 2 windows and 2 doors on penthouse with dual payne windows. not visible from street.Details
repair siding and waterproof windows on n/s of building. repair dry rot siding on penthouse, replace 2 windows and 2 doors on penthouse with dual payne windows. not visible from street. | $15,000 | |
| Jul 25, 2017 | Never finaled issued Jul 2017, no final | 1929 Stockton St | street spaceDetails
street space | ||
| Apr 25, 2017 | Never finaled issued Apr 2017, no final | 1931 Stockton St | street spaceDetails
street space | ||
| Feb 17, 2017 | Completed final sign-off Dec 2017 | 1929 Stockton St | strengthening existing roof sturcture.Details
strengthening existing roof sturcture. | $10,000 | |
| Feb 17, 2017 | Never finaled issued Feb 2017, no final | 7 Fielding St | at apartment building at b;pcl 0063,lot005. add addresses as 7,9,11 fielding street.Details
at apartment building at b;pcl 0063,lot005. add addresses as 7,9,11 fielding street. | ||
| Feb 13, 2017 | Completed final sign-off Feb 2017 | 1929 Stockton St | administrative permit to document this buildingat 1929-1933 stockton and 7-11 fielding st as a six unit building per city documents and site inspection (permit to validate record as six units rather than three unit in 3r report)Details
administrative permit to document this buildingat 1929-1933 stockton and 7-11 fielding st as a six unit building per city documents and site inspection (permit to validate record as six units rather than three unit in 3r report) | ||
| Jan 12, 2017 | Never finaled issued Jan 2017, no final | 1931 Stockton St | street spaceDetails
street space | ||
| Dec 1, 2016 | Never finaled issued Nov 2017, no final | 5 Fielding St | new one unit adu at 1st floor.Details
new one unit adu at 1st floor. | $85,000 | |
| Sep 13, 2016 | Completed final sign-off Oct 2017 | 1931 Stockton St | kitchen and bathroom repairs in kind. lathe and plaster repair. replace & repair where needed(damaged). no walls moved, removed or infilled. all existing layuts to remain unchanged.Details
kitchen and bathroom repairs in kind. lathe and plaster repair. replace & repair where needed(damaged). no walls moved, removed or infilled. all existing layuts to remain unchanged. | $20,000 | |
| May 19, 2016 | Expired or cancelled expired Nov 2019 | 1929 Stockton St | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4Details
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4 | $100,000 | |
| Apr 6, 2016 | Never finaled issued Apr 2016, no final | 1929 Stockton St | street spaceDetails
street space | ||
| Feb 25, 2016 | Completed final sign-off May 2018 | 1929 Stockton St | kitchen & bathroom - repairs in kind. lathe & plaster repair - replace & repair where needed. (damaged)Details
kitchen & bathroom - repairs in kind. lathe & plaster repair - replace & repair where needed. (damaged) | $15,000 | |
| Mar 6, 2014 | Expired or cancelled cancelled Jan 2026 | 1929 Stockton St | seismic upgrade for soft story. sfbc 34b using 2012 international existing building code appendix chapter 4a.Details
seismic upgrade for soft story. sfbc 34b using 2012 international existing building code appendix chapter 4a. | $40,000 | |
| Jun 1, 2004 | Never finaled issued Jun 2004, no final | 1929 Stockton St | L.C. General Builders Inc. | reroofingDetails
reroofing | $11,875 |
| May 28, 2004 | Never finaled issued May 2004, no final | 1929 Stockton St | street spaceDetails
street space |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Crime Watch Security Sys Llc (3), L.C. General Builders Inc., Project Contractor Inc
- Architects
- Suheil Shatara, William Pashelinsky, William Pashelinsky
- Engineers
- Matthew Tropp (2), Javed J. Tharavi
Find contractors for work like this