Joshua Toland
- Listed as
- authorized agent-others, contractor
- Firm
- Liquid Design Aquatic Consulting Company
- Based in
- Tracy
- On San Francisco permits
- Feb 2021 to Oct 2025
2 permits since 2000 (contractor on 2 permits, authorized agent-others on 1 permit): 2 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. Their ranked record as a contractor is on their contractor page. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 17, 2025 | Completed final sign-off Mar 2026 | 1075 California St | Liquid Design Aquatic Consulting Company | add steps for the swimming pool, replace equipment, replace coping plaster the pool.Details
add steps for the swimming pool, replace equipment, replace coping plaster the pool. | $100,000 |
| Feb 18, 2021 | Completed final sign-off May 2022 | 1001 Van Ness Av | Liquid Design Aquatic Consulting Company | gunite/concrete swimming pool construction. rebar reinforcing prior to gunite/concrete. rough plumbing of pool. rough electrical conduits for the pool lighting. bonding of the handrail anchors & ada lift anchor. supply and install cartridge filter, filter pump, heater, and chemistry control systemDetails
gunite/concrete swimming pool construction. rebar reinforcing prior to gunite/concrete. rough plumbing of pool. rough electrical conduits for the pool lighting. bonding of the handrail anchors & ada lift anchor. supply and install cartridge filter, filter pump, heater, and chemistry control system | $500,000 |