Permit GraphShortlistSan Francisco building permits since 2000

Patrick Fiedler

License
C38123
Architect or Civil engineer: both boards write C before the number, and the roles on the permits do not settle which
About the two boards
Look the license up with the state (Architects Board)
Look up C38123 at the Board for Professional Engineers
Listed as
architect, engineer
Firm
Fiedler Group
Based in
Pasadena
On San Francisco permits
Mar 2008 to Jun 2025

12 permits since 2000 (engineer on 10 permits, architect on 2 permits): 10 completed, 1 never finaled, 1 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Contractors
Fueling And Service Technologies Inc (6), Nicosia Consulting Internal Llc (3), Able Maintenance Inc, Gettler-Ryan Inc, Nel Hydrogen Inc, Stellar Building Services Inc.
Engineers
Dave Peyton (4), Sarah Nakhla

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jun 26, 2025Completed
final sign-off Jul 2025
1201 Harrison StFueling And Service Technologies Increvision to 202406275366 involving changes to ada path of traval & bollard's in the ada path (in front of the existing c-store) modification. all changes are on-site, no off-site work
Details
Permit
202506269559
Permit issued
Jun 26, 2025
Final sign-off
Jul 18, 2025

revision to 202406275366 involving changes to ada path of traval & bollard's in the ada path (in front of the existing c-store) modification. all changes are on-site, no off-site work

Open the permit page

$37,000
Oct 16, 2024Completed
final sign-off Jul 2025
1201 Harrison StFueling And Service Technologies Incremove/demo (e) hydrogen equip enclosure, tanks, 2 dispensers & associated equip/piping and electrical switcgear (remove/cap). remove piping trench and recompact. landscape and paving modifcations to affected areas. 3 new parking spaces. 1 new yard light. no new hydrogen equipment or enclosures.
Details
Permit
202406275366
Permit issued
Apr 9, 2025
Final sign-off
Jul 18, 2025

remove/demo (e) hydrogen equip enclosure, tanks, 2 dispensers & associated equip/piping and electrical switcgear (remove/cap). remove piping trench and recompact. landscape and paving modifcations to affected areas. 3 new parking spaces. 1 new yard light. no new hydrogen equipment or enclosures.

Open the permit page

$400,000
Oct 15, 2024Completed
final sign-off Aug 2025
551 03rd StAble Maintenance Incremove / demolish: hydrogen equipment enclosure, hydrogen tanks, 2 hydrogen dispensers, associated equipment / piping. underground remote offload vault, & electrical switchgear / low voltage panel (remove conductor / cap conduits). remove piping trench & recompact. landscape & paving modifications.
Details
Permit
202407015640
Permit issued
May 13, 2025
Final sign-off
Aug 22, 2025

remove / demolish: hydrogen equipment enclosure, hydrogen tanks, 2 hydrogen dispensers, associated equipment / piping. underground remote offload vault, & electrical switchgear / low voltage panel (remove conductor / cap conduits). remove piping trench & recompact. landscape & paving modifications.

Open the permit page

$400,000
Sep 23, 2024Completed
final sign-off Sep 2025
3550 Mission StFueling And Service Technologies Incremove/demolish: hydrogen equipment enclosure, hydro tanks, 2 hydro dispensers, associated equipment/piping, & elec transformer & switchgear. remove piping trench & recompact. landscape & paving modifications. relocate air/water unit, vacuum & 2 yard lights. remove & replace concrete swale near (e)
Details
Permit
202406265328
Permit issued
Apr 30, 2025
Final sign-off
Sep 2, 2025

remove/demolish: hydrogen equipment enclosure, hydro tanks, 2 hydro dispensers, associated equipment/piping, & elec transformer & switchgear. remove piping trench & recompact. landscape & paving modifications. relocate air/water unit, vacuum & 2 yard lights. remove & replace concrete swale near (e)

Open the permit page

$400,000
Apr 18, 2019Never finaled
issued May 2019, no final
1201 Harrison StFueling And Service Technologies Incfire alarm permit for (n) hydrogen fuel facility. ref permit# 201711133812. **maher n/a**
Details
Permit
201904188345
Permit issued
May 16, 2019

fire alarm permit for (n) hydrogen fuel facility. ref permit# 201711133812. **maher n/a**

Open the permit page

$10,000
Feb 6, 2019Completed
final sign-off Jan 2020
3550 Mission StNel Hydrogen Inc, Nicosia Consulting Internal Llcrevision to plans pa #201711133814. equipment compound shifted, same scope of work.
Details
Permit
201902062293
Permit issued
Apr 4, 2019
Final sign-off
Jan 27, 2020

revision to plans pa #201711133814. equipment compound shifted, same scope of work.

Open the permit page

Jan 30, 2019Completed
final sign-off Jul 2019
1201 Harrison StFueling And Service Technologies Increvision to issued permit #201711133812, structural sheet revision. maher na
Details
Permit
201901301636
Permit issued
Apr 10, 2019
Final sign-off
Jul 16, 2019

revision to issued permit #201711133812, structural sheet revision. maher na

Open the permit page

Nov 13, 2017Completed
final sign-off Jan 2020
3550 Mission StNicosia Consulting Internal Llcnew proposed hydrogen fule dispensers for passenger vehicles.associated equiptment foundations for auxilliary equiptment. ** maher: disturbance of at least 50 cu. yd of soil. route to dph **
Details
Permit
201711133814
Permit issued
Sep 27, 2018
Final sign-off
Jan 27, 2020

new proposed hydrogen fule dispensers for passenger vehicles.associated equiptment foundations for auxilliary equiptment. ** maher: disturbance of at least 50 cu. yd of soil. route to dph **

Open the permit page

$200,000
Nov 13, 2017Completed
final sign-off Jul 2019
1201 Harrison StFueling And Service Technologies Incnew proposed hydrogen fuel dispensers for passenger vehicles.associated equiptment foundations for auxilliary equiptment. ** maher: disturbance of at least 50 cu. yd of soil. route to dph **
Details
Permit
201711133812
Permit issued
Oct 4, 2018
Final sign-off
Jul 16, 2019

new proposed hydrogen fuel dispensers for passenger vehicles.associated equiptment foundations for auxilliary equiptment. ** maher: disturbance of at least 50 cu. yd of soil. route to dph **

Open the permit page

$200,000
Nov 8, 2017Completed
final sign-off Apr 2019
551 03rd StNicosia Consulting Internal Llcnew proposed hydrogen fuel dispensers for passenger vehicles.associated equipment foundation for auxilliary equiptment. at an existing gas station ** maher: disturbance of at least 50 cu. yd of soil. route to dph **
Details
Permit
201711083489
Permit issued
Sep 18, 2018
Final sign-off
Apr 9, 2019

new proposed hydrogen fuel dispensers for passenger vehicles.associated equipment foundation for auxilliary equiptment. at an existing gas station ** maher: disturbance of at least 50 cu. yd of soil. route to dph **

Open the permit page

$200,000
Aug 6, 2008Expired or cancelled
expired Mar 2022
1401 19th AvStellar Building Services Inc.ada access ramp at building entry. ada fixtures in restroom. ada counter at sales area. restriping ada parking area.
Details
Permit
200808068490
Permit issued
Aug 25, 2008

ada access ramp at building entry. ada fixtures in restroom. ada counter at sales area. restriping ada parking area.

Open the permit page

$20,000
Mar 25, 2008Completed
final sign-off Aug 2008
1288 19th AvGettler-Ryan Incinstall new clean air separator (heavy), new isd sensors at existing dispensers & enclosure.
Details
Permit
200803257882
Permit issued
Apr 15, 2008
Final sign-off
Aug 26, 2008

install new clean air separator (heavy), new isd sensors at existing dispensers & enclosure.

Open the permit page

$30,000