Justin David Maas
- License
- 84316
- Board not determined from the city's record: no role or letter places this number
- About the state's license search
- Search the state's license records (not the contractors board)
- Listed as
- engineer
- On San Francisco permits
- Feb 2020 to Jan 2023
3 permits since 2000 (engineer on 3 permits): 1 completed, 2 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records
Worked with
Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.
- Contractors
- E M A Builders Inc.
- Architects
- Andrew Carpentier
Where they worked
- Single-family 0
- Multi-family (2-family, apartments) 0
- Commercial 3
- Other or unknown 0
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 17, 2023 | Completed final sign-off Jan 2023 | 111 Powell St | E M A Builders Inc. | temporary retail pop up store inside existing vacant retail store. temporary wall panels supported by structural engineer design. temporary flooring at entry area, (e) flooring to remain. temp power for monitors and displays. pop up to open 1/25/2023 and run through 2/28/2023 then close and strike.Details
temporary retail pop up store inside existing vacant retail store. temporary wall panels supported by structural engineer design. temporary flooring at entry area, (e) flooring to remain. temp power for monitors and displays. pop up to open 1/25/2023 and run through 2/28/2023 then close and strike. | $197,222 |
| Feb 7, 2020 | Never finaled issued Feb 2020, no final | 44 Montgomery St | install temporary frame and connecting line for the purpose of filmimg for less than 30 days on the existing roof creating a guideline between one sansome and 44 montgomery.Details
install temporary frame and connecting line for the purpose of filmimg for less than 30 days on the existing roof creating a guideline between one sansome and 44 montgomery. | $10,000 | |
| Feb 7, 2020 | Never finaled issued Feb 2020, no final | 1 Sansome St | install temporary small frame and connecting line for the purpose of filming for less than 30 days into the existing window washer rig creating a guide line between one sansome and 44 montgomery street on top of the existing roof.Details
install temporary small frame and connecting line for the purpose of filming for less than 30 days into the existing window washer rig creating a guide line between one sansome and 44 montgomery street on top of the existing roof. | $10,000 |