# 505 Howard St

Permit 202505277274. Page: https://www.permitgraph.org/p/202505277274

installation of 2-boltdown level 2 ev chargers for used by valet service in garage. install (4) 40amp 2-pole breakers into existing electrical panel. run conduit on existing racks and pull wire to accommodate ev chargers. bolt down (2) bollards per charger.

- Outcome: Completed (city status: complete, Feb 18, 2026)
- Filed: Jun 6, 2025
- Permit issued: Nov 18, 2025
- Final sign-off: Feb 18, 2026
- Declared cost: $48,740
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Abm Electrical Solutions Dba Linc Lighti](https://www.permitgraph.org/contractor/abm-electrical-solutions-dba-linc-lighti-967676) (license 967676)
- Property: [All permits at this address](https://www.permitgraph.org/a/3736/183) (block 3736, lot 183)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Abm Electrical Solutions Dba Linc Lighti](https://www.permitgraph.org/contractor/abm-electrical-solutions-dba-linc-lighti-967676) (license 967676)
- Authorized agent: Nic Nowak, Abm Electrical Solutions (no license listed), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.