alterations to(e)lobby:demo & const of stairs & ramp,reception desk,guardrails & handrails.(e)(3)story elevator will be installed @ an adjacent location.finishes will be replaced incld paint,ceiling & floor.(n)arch lighting to be provided.mech & elec work limited to upgrades for renov & elevator.

- Outcome: In progress (city status: issued, Oct 1, 2025)
- Filed: Dec 21, 2023
- Permit issued: Oct 1, 2025
- Declared cost: $1,600,000
- Building use: school
- Neighborhood: Western Addition
- Contractor: [Guzman Construction Group Inc.](https://www.permitgraph.org/contractor/guzman-construction-group-inc-1010621) (license 1010621)
- Project type: Stairs
- Property: [All permits at this address](https://www.permitgraph.org/a/0737/001) (block 0737, lot 001)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Guzman Construction Group Inc.](https://www.permitgraph.org/contractor/guzman-construction-group-inc-1010621) (license 1010621)
- Architect: [Jeffrey Evans](https://www.permitgraph.org/professional/jeffrey-evans-C32430), Hkit Architects (license C32430), applicant
- Engineer: [Stephen R De Jesse](https://www.permitgraph.org/professional/stephen-r-de-jesse-S3527), Ida Structural (license S3527)
- Designer: Stan Lam, Hkit Architects (no license listed)
- Pmt consultant/expediter: Stan Lam (no license listed)

---