Permit 202312192806
949 Capp St
to comply with nov 202315282: item #2repair garage ceiling opening due to plumbing repair (approx. 2'x3' area)
- Outcome
- Completed (city status: complete, Jan 18, 2024)
- Filed
- Dec 19, 2023
- Permit issued
- Dec 20, 2023
- Final sign-off
- Jan 18, 2024
- Declared cost
- $200
- Building use
- apartments
- Neighborhood
- Mission
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 6518, lot 019)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder