***priority process*install electric vehicle infrastructure to support 89 charge ports for an existing service yard (no change of use). a total of (25) 19.2kw ac level 2 ports, (20) 22.5kw dc wallbox ports, (4) 92kw dcfc ports and associated electrical equipment will be installed. additionally,

- Outcome: In progress (city status: issued, Dec 11, 2025)
- Filed: Jul 3, 2023
- Permit issued: Dec 11, 2025
- Declared cost: $581,065
- Building use: parking lot
- Neighborhood: Mission
- Contractor: [W. Bradley Electric](https://www.permitgraph.org/contractor/w-bradley-electric-1114449) (license 1114449)
- Property: [All permits at this address](https://www.permitgraph.org/a/3592/030) (block 3592, lot 030)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [W. Bradley Electric](https://www.permitgraph.org/contractor/w-bradley-electric-1114449) (license 1114449)
- Engineer: [Douglas Karlsberg](https://www.permitgraph.org/professional/douglas-karlsberg-E23052), Burns &Mcdonnell Eng (license E23052)
- Engineer: [Kevin Wei](https://www.permitgraph.org/professional/kevin-wei-C92903) (license C92903)
- Engineer: [Mohand Abodia](https://www.permitgraph.org/professional/mohand-abodia-C88279), Burns &Mcdonnell Engineering (license C88279)
- Authorized agent: Janelle Cruz, Burns & Mcdonnell Eng (no license listed), applicant
- Authorized agent: [Sara Burtz](https://www.permitgraph.org/professional/sara-burtz-1114449), W. Bradley Electric (license 1114449)

---