# 28 Bruton St

Permit 202211297332. Page: https://www.permitgraph.org/p/202211297332

fire only review of generator & fuel storage only. bruton st. pump station generator permit in support of puc infrastructure, plans previosly reviewed& approved by dpw ahead of installation in field, permit intended to facilitate fire dept. inspection of as-built conditions.

- Outcome: Completed (city status: complete, Apr 3, 2023)
- Filed: Nov 29, 2022
- Permit issued: Mar 17, 2023
- Final sign-off: Apr 3, 2023
- Building use: sewage plant
- Neighborhood: Treasure Island
- Contractor: [De Silva Gates Construction](https://www.permitgraph.org/contractor/de-silva-gates-construction-704195) (license 704195)
- Property: [All permits at this address](https://www.permitgraph.org/a/8902/465) (block 8902, lot 465)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [De Silva Gates Construction](https://www.permitgraph.org/contractor/de-silva-gates-construction-704195) (license 704195)
- Engineer: [Christopher Guillard](https://www.permitgraph.org/professional/christopher-guillard-5993) (license 5993)
- Engineer: [Diep Nguyen](https://www.permitgraph.org/professional/diep-nguyen-10867) (license 10867)
- Engineer: [Julio C. Herdocia](https://www.permitgraph.org/professional/julio-c-herdocia-9580) (license 9580)
- Engineer: [Thomas Morse](https://www.permitgraph.org/professional/thomas-morse-49457) (license 49457)
- Authorized agent: David Lu, Gary Bell & Associates Inc. (no license listed), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.