Permit GraphShortlistSan Francisco building permits since 2000

Permit 202209142421

1234 Grove St

retrofit to comply with nov 202294960. soft story retrofit of the ground story with additional wood sheathed shear walls with new and retrofitted foundations and diaphragm connections under the first floor. (asce 41-13 enginnering criteria)

Outcome
Completed (city status: complete, Mar 31, 2023)
Filed
Sep 14, 2022
Permit issued
Dec 21, 2022
Final sign-off
Mar 31, 2023
Declared cost
$100,000
Building use
apartments
Neighborhood
Hayes Valley
Contractor
Sandbank Construction, Inc (license 893993)
Property
All permits at this address (block 1181, lot 011)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Sandbank Construction, Inc (license 893993)
Engineer
Tyler Moser, Halyard Inc (license C84735)