# 2501 03rd St

Permit 202208160595. Page: https://www.permitgraph.org/p/202208160595

att modifcation of unmanned telecom facility, remove (9)panel antennas, (6)new, remove (3)rrus, install (3)6 awg power trunk cables. new rf safety signs, barricade/striping rooftop, install (1)new rectifier in e dc power plant, (1)new 6648 baseband unit in existing purcell cabinet

- Outcome: Completed (city status: complete, Jun 5, 2024)
- Filed: Aug 16, 2022
- Permit issued: Jul 19, 2023
- Final sign-off: Jun 5, 2024
- Declared cost: $55,000
- Building use: office
- Neighborhood: Potrero Hill
- Contractor: [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) (license 401047)
- Property: [All permits at this address](https://www.permitgraph.org/a/4173/001) (block 4173, lot 001)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) (license 401047)
- Engineer: [Seung Kun Oh](https://www.permitgraph.org/professional/seung-kun-oh-C84365), J5 Infrasture Partners (license C84365)
- Authorized agent: Alejandro Lagunas, Metropolitan Electrical Constr (no license listed), applicant
- Lessee: Asb Capital Mgt Llc Asb 795 Folsom Llc, Asb 795 Folsom Llc (no license listed)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.