Permit 202205023411

84 Molimo Dr

corrective permit to document the construction work to comply with nov #201956581 "excavation, foundation and structural work, performed without permit, violation has been addressed undrer previously approved permit pa# 2019-0520-1153 ref drawngs s2.1, s3.1,s4.1,s4.2

Outcome
Completed (city status: complete, Jul 19, 2022)
Filed
May 2, 2022
Permit issued
May 3, 2022
Final sign-off
Jul 19, 2022
Declared cost
$40,000
Building use
1 family dwelling
Neighborhood
West of Twin Peaks
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 2999B, lot 034)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner
Engineer
Peter Zepponi (license C26699), applicant