Permit GraphShortlistSan Francisco building permits since 2000

Permit 202202248612

745 Buchanan St

amend to pa202112214819 for additional work. remove (e) windows & replace same style of 20 additional windows. replace (e) opening. u=.30max

Outcome
Completed (city status: complete, Feb 26, 2024)
Filed
Feb 24, 2022
Permit issued
Feb 24, 2022
Final sign-off
Feb 26, 2024
Declared cost
$15,000
Building use
recreation bldg
Neighborhood
Hayes Valley (how long permits take there)
Contractor
Paramount Construction (license 520230)
Property
All permits at this address (block 0805, lot 003)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Paramount Construction (license 520230), applicant