# 121 Steuart St

Permit 202112214790. Page: https://www.permitgraph.org/p/202112214790

at&t: replace 10 antennas, remove 3 rru's, relocate 4 rru's, install 3 diplexers, remove 2 cabinets, remove 1 dus41, remove 12 batteries, install 2 rectifiers, install 1 battery rack with 8 strings of batteries, install 12 batteries.

- Outcome: Completed (city status: complete, Nov 22, 2022)
- Filed: Dec 21, 2021
- Permit issued: May 4, 2022
- Final sign-off: Nov 22, 2022
- Declared cost: $25,000
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) (license 401047)
- Property: [All permits at this address](https://www.permitgraph.org/a/3715/003) (block 3715, lot 003)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) (license 401047)
- Engineer: [Eric William Karstetter](https://www.permitgraph.org/professional/eric-william-karstetter-E23512) (license E23512)
- Engineer: [Seung Kun Oh](https://www.permitgraph.org/professional/seung-kun-oh-C84365), J5 Infrasture Partners (license C84365)
- Authorized agent: Charlene Schlager, J5 Infrastructure (no license listed), applicant
- Lessee: At And T Mobility (no license listed)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.