# 820 Visitacion Av

Permit 202108247052. Page: https://www.permitgraph.org/p/202108247052

rev pa202107275170 - add 1 full bathroom on 2/f.

- Outcome: Completed (city status: complete, Oct 13, 2021)
- Filed: Aug 24, 2021
- Permit issued: Aug 24, 2021
- Final sign-off: Oct 13, 2021
- Declared cost: $10,000
- Building use: 1 family dwelling
- Neighborhood: Visitacion Valley
- Contractor: [Kevin Lin Construction Inc](https://www.permitgraph.org/contractor/kevin-lin-construction-inc-1004147) (license 1004147)
- Project type: Bathroom remodel
- Property: [All permits at this address](https://www.permitgraph.org/a/6251/008A) (block 6251, lot 008A)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Kevin Lin Construction Inc](https://www.permitgraph.org/contractor/kevin-lin-construction-inc-1004147) (license 1004147)
- Designer: Anita Zhu, Hing Wah Construction (no license listed)
- Pmt consultant/expediter: Ava Lui, Hing Wah Construction (no license listed), applicant

---