# 1185 Market St

Permit 202104067981. Page: https://www.permitgraph.org/p/202104067981

install 800a switchboard to feed (1) all-in-one 50kw ev charger & (4) all-in-one 100kw ev chargers. install associated conduit & conductors. (5) total evcs being installed as part of approved (12) future ev chargers approved for whole foods market renovation under pa# 202007200503.

- Outcome: Completed (city status: complete, Dec 3, 2021)
- Filed: Apr 6, 2021
- Permit issued: Oct 8, 2021
- Final sign-off: Dec 3, 2021
- Declared cost: $350,000
- Building use: retail sales
- Neighborhood: South of Market
- Contractor: [Cupertino Electric Inc.](https://www.permitgraph.org/contractor/cupertino-electric-inc-174637) (license 174637)
- Property: [All permits at this address](https://www.permitgraph.org/a/3702/390) (block 3702, lot 390)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Cupertino Electric Inc.](https://www.permitgraph.org/contractor/cupertino-electric-inc-174637) (license 174637)
- Engineer: [John Bachoua](https://www.permitgraph.org/professional/john-bachoua-19677), Nazarene Engineering (license 19677)
- Engineer: [Marshall Pfeiffer](https://www.permitgraph.org/professional/marshall-pfeiffer-5013) (license 5013)
- Authorized agent: Justin Cheung, Evgo Services Llc (no license listed), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/202104067981.