Permit 202102184896
150 Guerrero St
remodel of adjacent master & guest bathrooms on 3rd floor. new fixtures & finishing. removal of 1 wall & moving another wall. replace tub in guest bathroom. new tiling for walls & floors in wet areas. new paint & lighting throughout.
- Outcome
- Completed (city status: complete, Nov 8, 2021)
- Filed
- Feb 18, 2021
- Permit issued
- Apr 28, 2021
- Final sign-off
- Nov 8, 2021
- Declared cost
- $36,000
- Building use
- apartments
- Neighborhood
- Mission
- Contractor
- Peters Construction (license 993709)
- Project type
- Bathroom remodel
- Property
- All permits at this address (block 3534, lot 103)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Peters Construction (license 993709)
- Designer
- Kevin Mole, Project Haven (no license listed), applicant