Permit 202010015657
908 Post St
building permit for remodel in kind for 4th fl rooms 22, 27, 28, 29, 30, 31 to comply with nov 202052031
- Outcome
- Completed (city status: complete, May 9, 2023)
- Filed
- Oct 1, 2020
- Permit issued
- Oct 1, 2020
- Final sign-off
- May 9, 2023
- Declared cost
- $20,000
- Building use
- power plant
- Neighborhood
- Nob Hill (how long permits take there)
- Contractor
- S F Garage Company Inc. (license 684863)
- Property
- All permits at this address (block 0301, lot 007)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- S F Garage Company Inc. (license 684863)