# 2844 Lyon St

Permit 202008061263. Page: https://www.permitgraph.org/p/202008061263

add four (4) units per ord# 162-16. convert (e) garage & crawl space into new dwelling units within (e) envelope. new bathrooms, bedrooms, dishwashers, washer/dryers. seismic retrofit unde pa ~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&~encrypt&

- Outcome: Completed (city status: complete, May 28, 2025)
- Filed: Aug 6, 2020
- Permit issued: Oct 24, 2022
- Final sign-off: May 28, 2025
- Declared cost: $200,000
- Building use: apartments
- Neighborhood: Marina
- Contractor: [Halyard Inc](https://www.permitgraph.org/contractor/halyard-inc-1049217) (license 1049217)
- Project type: Bathroom remodel
- Property: [All permits at this address](https://www.permitgraph.org/a/0941/024) (block 0941, lot 024)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Halyard Inc](https://www.permitgraph.org/contractor/halyard-inc-1049217) (license 1049217)
- Architect: [Jacob Herczeg](https://www.permitgraph.org/professional/jacob-herczeg-C34024), Halyard Construction Inc. (license C34024), applicant
- Engineer: [Tyler Moser](https://www.permitgraph.org/professional/tyler-moser-C84735), Halyard Inc (license C84735)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.