# 410 Townsend St

Permit 201911066558. Page: https://www.permitgraph.org/p/201911066558

upgrading path of travel elements. installation of new wheel guards at lobby pedestrian ramp, new door opener at exterior entrance, and truncated domes and signage at basement level.

- Outcome: Completed (city status: complete, Aug 6, 2020)
- Filed: Nov 6, 2019
- Permit issued: Dec 11, 2019
- Final sign-off: Aug 6, 2020
- Declared cost: $15,000
- Building use: office
- Neighborhood: Mission Bay
- Contractor: [Bevilacqua & Sons](https://www.permitgraph.org/contractor/bevilacqua-sons-732067) (license 732067)
- Property: [All permits at this address](https://www.permitgraph.org/a/3785/002A) (block 3785, lot 002A)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Bevilacqua & Sons](https://www.permitgraph.org/contractor/bevilacqua-sons-732067) (license 732067)
- Architect: Alodie Girmann, Revel Architecture & Design (no license listed)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/201911066558.