# 2522 Post St

Permit 201905302068. Page: https://www.permitgraph.org/p/201905302068

to obtain final inspection for work approved under pa# 201510200272. all work is complete.

- Outcome: Completed (city status: complete, Mar 13, 2020)
- Filed: May 30, 2019
- Permit issued: May 30, 2019
- Final sign-off: Mar 13, 2020
- Building use: apartments
- Neighborhood: Presidio Heights
- Contractor: [Payesko Constructioin Inc](https://www.permitgraph.org/contractor/payesko-constructioin-inc-775914) (license 775914)
- Property: [All permits at this address](https://www.permitgraph.org/a/1074/010) (block 1074, lot 010)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Payesko Constructioin Inc](https://www.permitgraph.org/contractor/payesko-constructioin-inc-775914) (license 775914)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/201905302068.