# 315 Montgomery St

Permit 201905130410. Page: https://www.permitgraph.org/p/201905130410

2nd floor:relocation of a door to provide a fully accessible ramp landing. addition of a vestibule door with card access. no change in occupancy. n/a for maher

- Outcome: Completed (city status: complete, Aug 21, 2019)
- Filed: May 13, 2019
- Permit issued: May 16, 2019
- Final sign-off: Aug 21, 2019
- Declared cost: $9,189
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Bcci Construction Company](https://www.permitgraph.org/contractor/bcci-construction-company-492944) (license 492944)
- Property: [All permits at this address](https://www.permitgraph.org/a/0259/029) (block 0259, lot 029)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Bcci Construction Company](https://www.permitgraph.org/contractor/bcci-construction-company-492944) (license 492944)
- Architect: Huntsman Arch. (no license listed)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/201905130410.